top of page
NEC checklists and tools
Checklists to download and use on a live NEC job: programme acceptance, payment applications, compensation event quotations and extension of time claims.
Search


NEC4 payment applications: what to submit, what gets certified and when you are paid
Under NEC4 the assessment date arrives whatever has been filed, and a month without an application is a month without an increase. This guide walks the payment clauses from the contractor's side: what the application must show on each main Option, the certificate and interest, pay less notices under Y(UK)2, how the programme controls the cash, and the clause 53 final assessment. With a two-page Payment Application Checklist.
Oct 2914 min read


The NEC Compensation Event Quotation: How the Money Is Built
A compensation event quotation has two limbs, time and money, and the money is the one contractors price worst. This is the guide to the change to the Prices: how it is built from Defined Cost and the Fee under clause 63.1, why your tendered rates usually do not apply, where your overhead and profit actually sit, why the forecast you agree is final, and the handful of points where valid entitlement quietly leaks away in the pricing.
Aug 2011 min read


NEC Programme Not Accepted: The Clause 31.3 Response Playbook
The notice says not accepted, and what happens next decides more than the fate of one submission. This playbook covers the moment in full: the four reasons Clause 31.3 permits and why they are the only four, the detail a notice must give you under Clause 13.4, the triage that sorts right from wrong from unclear, when withholding acceptance becomes a compensation event under 60.1(9), and the cost of drifting while the Accepted Programme goes stale.
Aug 1610 min read


FIDIC extension of time: Sub-Clause 8.5, the 20.2 claim and the programme behind it
A FIDIC extension of time is decided on the programme and the records. This guide takes the 2017 Red and Yellow Books from the planner's side: the Sub-Clause 8.5 grounds and what each carries, the Notice of Claim and fully detailed Claim under 20.2 with the Engineer's 14 days and the late-submission review, the 42 plus 42 days under 3.7, concurrent delay, the programme evidence that wins the days, and what an EU grant adds on funded work.
Jun 2717 min read


Assessing NEC4 compensation events: 5 judgement calls
Give the same compensation event to two competent planners. Same accepted programme, same dividing date, same facts. One comes back with three weeks of delay to planned Completion. The other comes back with nine days. Both can defend their model. Neither has made an arithmetic error. The difference is five judgement calls that sit inside every NEC4 delay assessment, that the contract deliberately leaves open, and that most contractors make silently.
Aug 3, 202513 min read
Need help on a live NEC job?
The guides explain the rules. On a 30-minute call we talk through your programme, notice or quotation and what to do next. The call is confidential and you don't need to send anything first.
​
Scope confirmed before billing
bottom of page