top of page

PRE-CONSTRUCTION PLANNING

Pre-construction planning from award to site start

Pre-construction planning services for contractors between award and site start. The first programme ready for acceptance, long-lead procurement inside the logic and the controls set up before site starts. A first programme from £1,250 + VAT.

Sample pre-construction pack on a demo NEC4 project: first programme dates, long-lead procurement and controls set-up

Sample pre-construction pack on a demo project. Opens as a PDF.

NEC ACCREDITED

APMG QUALIFIED

P6 / MS PROJECT / ASTA

NEC / JCT / FIDIC

THE FIRST WEEKS AFTER AWARD

What the contract asks for between award and site start

The contract clock starts at award, usually before the site team is in place. These are the first dates under NEC4, with the FIDIC and JCT equivalents below them.

1

2

3

4

5

Award

CONTRACT DATE

The Contract Date, when the contract comes into existence. The period for the first programme runs from here, not from the starting date.

Starting date

CLAUSES 15.1 AND 15.2

The Project Manager issues the first Early Warning Register within one week. The Contractor and the Project Manager give an early warning as soon as either becomes aware of a matter that could increase the total of the Prices or delay Completion.

First programme submitted

Where the Contract Data identifies no programme, the first one is due within the period it states. The clause sets no default period.

CLAUSE 31.1

Project Manager's reply

CLAUSE 31.3

Acceptance or reasons within two weeks. If the reply is late, the Contractor may notify it and a further week of silence is treated as acceptance.

First assessment

CLAUSE 50.5 · NEC3 50.3

Until a first programme with the information the contract requires is submitted, a quarter of the Price for Work Done to Date is retained.

Where the Contract Data already identifies a programme, clauses 31.1 and 50.5 do not apply. FIDIC 2017: the initial programme within 28 days of receiving the Notice under Sub-Clause 8.1 (Sub-Clause 8.3). JCT SBC 2016: the master programme as soon as possible after the contract is executed, unless already provided (clause 2.9.1.2).

WHAT MAKES THIS DIFFERENT

Why pre-construction planning decides how the project runs

Built for the team that runs the job, not for the bid file.

Long-lead items sit in the logic

Order, approval, manufacture and delivery are activities with dates, linked to the work that needs them. A late approval then shows in the programme while there is still time to act.

A first programme built to be accepted

Built to the clause 31.2 list, with a narrative the Project Manager can test against the Scope. Submitted with the information the contract requires, it ends the quarter retention where clause 50.5 applies.

Controls set up before site starts

Coding, calendars, cut-off dates and the report format agreed before the first update. Assumptions written down now are the record a later compensation event can rely on.

Pre-construction through to completion. On a £20M carbon capture facility, NEC Planning Solutions was engaged from tender stage through pre-construction and into live delivery, building the baseline programme from first principles and maintaining it through continuous design change to practical completion. View case study

OUTPUTS

What our pre-construction planning services include

Five outputs, issued together as one pack and reviewed before issue.

FOUNDATION OUTPUT

First programme for acceptance

  • Logic-linked from award to planned Completion, with the Key Dates and the Completion Date

  • To clause 31.2 under NEC, Sub-Clause 8.3 under FIDIC 2017 or clause 2.9 under JCT SBC 2016

  • Native file in P6, MS Project or Asta, with a PDF for submission

INTERFACE OUTPUT

Constraints and interface plan

  • Access dates, permits and possessions built into the logic

  • Design, third-party and client interfaces with the date each side needs

  • Each assumption written down, so a later change can be measured against it

PROCUREMENT OUTPUT

Long-lead procurement schedule

  • Each long-lead item from order to delivery, linked to the work it feeds

  • Design approvals and submittal dates tied to the programme

  • Float on each item shown, so the late ones are seen early

NARRATIVE OUTPUT

Programme narrative

  • For each operation, how the work will be done and the principal Equipment and other resources, as clause 31.2 asks

  • Assumptions, exclusions and the dates the Contractor needs access, acceptances and information

  • Written for the Project Manager to read, not to file

CONTROLS OUTPUT

Controls set-up

  • Coding, calendars and activity naming fixed before the first update

  • Cut-off dates, progress rules and the update cycle agreed

  • The report pack and its readers, handed over in a session with your team

WHO IT'S FOR

Contractors with a short window between award and site start

Most useful where access, permits, interfaces, long-lead items or unfinished design will shape the first months on site. It also fits a PCSA or an early contractor involvement stage.

WORKS FOR

Main contractors
Civil contractors
M&E contractors
Infrastructure teams
Energy & renewables
Data centre projects
Industrial contractors
Asset owners

HOW IT WORKS

How the pre-construction planning works

Scope and fee agreed in writing before any chargeable work. A first programme for a single-phase job is ready within 5 working days of that agreement.

STAGE 01

Confirm the scope

We read the contract, the Scope and what exists from tender, then agree the outputs, the fee and the dates.

WRITTEN SCOPE BEFORE BILLING

STAGE 02

Build and review

Programme, procurement, interfaces and narrative built together, then checked against the contract before issue.

SENIOR REVIEW BEFORE ISSUE

STAGE 03

Hand over

The pack goes to your team in a working session, ready for the first submission and the first update.

FULL PACK AND HANDOVER SESSION

PRICING

Pre-construction planning prices, agreed before work starts

Priced by the number of phases, interfaces and long-lead items. A fixed fee where the scope allows.

ENGAGEMENT STRUCTURE

FIXED-FEE OPTIONS

SCOPE CONFIRMED IN WRITING

FIRST PROGRAMME IN 5 WORKING DAYS

CONFIDENTIAL

Fixed fee where scope allows, otherwise a defined upper limit. Confirmed before any chargeable work begins.

Outputs, fee and timeline confirmed before chargeable work begins.

On a single-phase job, counted from the day the scope is agreed.

Your contract documents and programmes are used for your job only.

FIRST PROGRAMME

From £1,250 + VAT

SINGLE PHASE, FEW INTERFACES

A first programme ready for acceptance, with its narrative, within 5 working days of the scope being agreed.

PRE-CONSTRUCTION PACK

From £2,500 + VAT

PROGRAMME, PROCUREMENT AND CONTROLS

All five outputs in one pack, with a handover session for your team.

COMPLEX SCOPE

Scoped

MULTI-PACKAGE, INFRASTRUCTURE OR ENERGY

Several phases or packages, possessions or outages. Priced once we understand the packages and the dates.

Every fee is confirmed in writing before any chargeable work.  See full pricing

QUESTIONS

Common questions about pre-construction planning services

How much do pre-construction planning services cost?

A first programme for a single-phase job starts from £1,250 + VAT. The full pre-construction pack, with procurement, interfaces and the controls set-up, starts from £2,500 + VAT. Larger multi-package jobs are scoped. The fee is confirmed in writing before any chargeable work.

How quickly can a first programme be ready?

Within 5 working days of the scope being agreed, for a single-phase job. Under NEC4, where the Contract Data identifies no programme, the first programme is due within the period the Contract Data states (clause 31.1), so the best time to start is at award.

What happens if the first programme is late under NEC4?

Where the Contract Data identifies no programme, one quarter of the Price for Work Done to Date is retained until a first programme with the information the contract requires is submitted (clause 50.5, 50.3 in NEC3). Until a programme is accepted, the Project Manager also uses its own assessment of the programme when it assesses a compensation event itself (clause 64.2).

Does it work under a PCSA or early contractor involvement?

Yes. Under a pre-construction services agreement or an early contractor involvement stage (NEC4 Option X22, used with Options C and E), the same pack sets up the programme and procurement before the main works. Our PCSA guide covers the obligations a PCSA can carry.

What do you need from us?

Nothing to start the conversation. Once the scope is agreed, we work from the contract, the Scope, the tender programme if there is one and the procurement list. Everything stays confidential.

Need a programme ready before site start?

Tell us the contract, the award date and when site starts. We will confirm the scope and fee in writing before any chargeable work begins.

You don't need to send anything first.

bottom of page