top of page

PRE-CONSTRUCTION PLANNING

Pre-construction planning that decides how the project runs

We turn the mobilisation window into a working programme the delivery team can run for the next eighteen months, not a document that gets shelved once site starts.

NEC ACCREDITED

APMG QUALIFIED

P6 / MS PROJECT / ASTA

NEC / JCT / FIDIC

WHERE THIS FITS

What happens in the mobilisation window

Between contract award and site start, five things need to happen in the right order. This is the stage most teams underplan. What gets set up here runs for the whole project.

âś“

2

3

4

Contract
Awarded

Tender accepted.
Clock starts.

Scope &
Constraints Mapped

Access windows, permits, interfaces and design dependencies confirmed and embedded in the logic.

Programme
Built & Assured

Logic-linked programme with procurement integrated, milestones set and reviewed before issue.

Baseline Locked &
Controls Set Up

Update cadence, cut-offs, progress rules and reporting format agreed and handed to the delivery team.

Site Start /
Mobilisation

Delivery team starts with a programme they can actually use and report against.

Without this: assumptions buried in a spreadsheet

Without this: no credible baseline to update from

Without this: reporting drifts from week one

The critical window

Stages 2–4 are where this service operates. Typically 4–12 weeks between award and site start, compressed on fast-track or framework projects.

WHAT MAKES THIS DIFFERENT

Set up to control, not just to start

Most pre-construction planning is built for the pitch. This is built for the delivery team that has to run it for the next eighteen months.

- 01

01

Procurement belongs in the logic, not in a separate spreadsheet

Long-lead items, work packages and material dependencies tied directly into the programme sequence. So "materials on site" is never an assumption. It is a date with a driver, visible in the critical path from day one.

- 02

02

The controls decisions made here run for the whole project

WBS coding, update cadence, cut-off rules, progress rules, reporting format. Everything the delivery team needs to run consistent updates. Agreed in pre-construction so the baseline lock is not a discussion at the first site meeting.

- 03

03

A stronger commercial position from the start of delivery

Clear assumptions, documented constraints and traceable interfaces mean that when change and delay need to be evidenced later, the record starts now, not reconstructed under pressure six months in.

Pre-construction through to completion. On a £20M carbon capture facility, NEC Planning Solutions was engaged from tender stage through pre-construction and into live delivery, building the baseline programme from first principles and maintaining it through continuous design change to practical completion. View case study ›

OUTPUTS

What the pre-construction pack contains

Five outputs that form a single hand-over pack: programme, constraints, procurement, narrative and controls set-up. Issued together so the delivery team has everything in one place.

FOUNDATION OUTPUT

Pre-construction programme & milestone plan

A logic-linked programme covering key stages, milestones and handovers, aligned to the intended construction approach and client submission expectations. Built in P6, MS Project or Asta.

  • Logic-linked schedule from award to site start

  • Key stages, milestones and handover dates

  • Contract submission format where required (NEC Cl.31/32, JCT, FIDIC)

  • Reviewed by an NEC Accredited Project Manager before issue

INTERFACE OUTPUT

Constraints & interface plan

A practical map of access windows, permits, third-party dependencies, design interfaces and commissioning requirements, embedded in the programme logic, not listed separately.

  • Access windows and permit requirements

  • Third-party and design interfaces

  • Commissioning and handover constraints

  • Interface assumptions documented for change reference

PROCUREMENT  OUTPUT

Procurement & long-lead integration

Key long-lead items and work packages tied into the programme sequence so delivery dates are driven by logic, not assumption. Particularly critical on M&E, energy and industrial projects.

  • Long-lead items identified and sequenced

  • Work package dates tied to programme logic

  • Procurement float and risk identification

  • Materials-on-site dates visible in critical path

NARRATIVE OUTPUT

Programme narrative: basis of schedule

A concise written basis of schedule covering assumptions, constraints, key dates, sequencing rationale and interfaces. Suitable for internal governance, client submission and audit review.

  • Sequencing rationale and constraint descriptions

  • Assumptions explicitly listed, not buried

  • Key dates and interface responsibilities

  • Submission-ready for client review

CONTROLS OUTPUT

Mobilisation & controls set-up

The agreed structure the delivery team needs to run consistent, credible updates from day one without reinventing it at the first site meeting. This is the output that makes everything else sustainable through the delivery phase.

  • WBS coding structure and activity naming conventions

  • Calendar and data-date discipline agreed

  • Progress rules and cut-off schedule confirmed

What gets handed over

  • Update cadence and reporting rhythm confirmed in writing

  • Reporting pack format and stakeholder distribution agreed

  • Handover brief: how this programme is run and updated

  • Optional: Programme Assurance Passport: a one-page governance summary for audit or client governance requirements

WHO IT'S FOR

Delivery teams preparing to start site, where the mobilisation window is finite

Particularly valuable where interfaces, access constraints, permits, long-lead procurement or design maturity can make or break the first 8–12 weeks.

WORKS FOR

Main contractors
Civil contractors
M&E contractors
Infrastructure teams
Energy & renewables
Data centre projects
Industrial contractors
Asset owners

HOW IT WORKS

From award to handover in three stages

No preparation needed. Send us the contract documents and what you have from tender. We'll confirm scope and fee in writing before any chargeable work begins.

STAGE 01

Define & align

Confirm scope boundaries, key dates, constraints, interfaces and the intended construction approach. Agree what "good" looks like: stakeholder needs, client submission requirements and what the delivery team will need to run updates.

Written scope before billing

STAGE 02

Build, integrate and review

Develop the programme logic, integrate constraints, procurement and interfaces, apply NEC-accredited governance checks. Produce the programme narrative in parallel so both documents tell the same story before they leave us.

NEC-accredited governance check

STAGE 03

Hand over & mobilise

Issue the full pre-construction pack: programme, narrative, constraints summary and controls set-up, with a brief handover session so the delivery team can run updates from the first data date without reinventing anything.

Full pack · Handover session

PRICING

Scoped to your project, confirmed before billing

Pre-construction pricing reflects the complexity of your constraints, interface count, procurement scope and the controls set-up required. Exact fee is confirmed after a short review of your project documents.

ENGAGEMENT STRUCTURE

FIXED-FEE OPTIONS

Fixed fee where scope allows, otherwise a defined upper limit. Confirmed before any chargeable work begins.

SCOPE CONFIRMED IN WRITING

Outputs, fee and timeline confirmed before chargeable work begins.

INITIAL SCOPING AT NO CHARGE

A short call to confirm fit, scope and next step.

MINIMUMS AGREED UPFRONT

Any monthly cycle or minimum period is confirmed before work starts.

NEW £

Smaller scope

From £2,000

Single-phase, limited interfaces

Pre-construction pack with programme, narrative and controls set-up.

Standard scope

From £4,000

Multi-interface or procurement-heavy

Constraints plan, procurement integration, handover session. Built so the controls team can pick it up.

NEW £

Complex scope

Scoped

Infrastructure, energy, multi-package

Scoped after project documents reviewed. Larger programmes and multi-package delivery.

LIVE

Pricing confirmed after a short review of your contract documents and scope.  See full pricing

RELATED

What comes before and after pre-construction

Pre-construction sits between tender and live delivery. These services connect directly to this stage.

Ready to set up delivery properly?

Tell us the contract type, project stage and your site start date. We'll confirm the right scope and fee in writing before work begins, and we can turn a pre-construction pack around inside your mobilisation window.

Or send your current programme for an initial review of logic at no charge and contract alignment. No obligation to proceed.

Initial programme review at no charge, with no obligation to proceed.

bottom of page