12 months
SINCE THE LAST ACCEPTED PROGRAMME, WHEN WE JOINED
18 months
OF MONTHLY PROGRAMMES, EVERY ONE ACCEPTED
7
COMPENSATION EVENTS BUILT INTO THE PROGRAMME
Compensation events piling up on a year-old programme
A £50M+ upgrade of the M&E and civil infrastructure at a major gas terminal on Scotland's north-east coast, under NEC3 Option A.
When we joined the contractor's team in 2023, the Accepted Programme was a year old. Every compensation event was assessed against that out-of-date programme. Each one was harder to agree, so they piled up.
What we did
A clause 32 programme every month
A revised programme under clause 32 every month, in Primavera P6, showing the actual progress, the effects of implemented compensation events and how the Contractor planned to deal with delays.
Compensation events on the programme
Each of the seven compensation events built into the programme, so its effect on planned Completion was in front of the Project Manager with every revision.
Lookaheads, earned value and a deliverables tracker
Rolling lookaheads for the site teams, earned value analysis for the commercial team and a key deliverables tracker for management, all from the same programme.
In the team to Completion
Full-time in the contractor's team as Senior Planning Engineer, from 2023 to Completion.
The result
The programme went from a year without acceptance to a revision accepted every month for 18 months, so compensation events were assessed against a current programme. They moved the Completion Date later. The programme showed the effect of each one.