FOR PROJECT MANAGERS AND CLIENTS

NEC Project Manager support for programmes and compensation events

Under NEC3 and NEC4 the Project Manager has two weeks to reply to a programme and two weeks to reply to a quotation. We review the Contractor's submission within 5 working days of it reaching us for a programme and 3 for a quotation, with your reasons set out in the contract's terms.

You don't need to send anything first.

2 weeks

TO REPLY TO A PROGRAMME OR A QUOTATION

5 working days

FOR OUR PROGRAMME REVIEW TO REACH YOU

3 working days

FOR OUR QUOTATION CHECK TO REACH YOU

What we review for you

ACCEPT

Programmes submitted for acceptance

We check the programme against what clause 31.2 says it must show and against the Scope (the Works Information under NEC3). Any reason not to accept it is set out as one of the four in clause 31.3, ready for your reply.

CONTROL

Revised programmes, with a report to the client

We check each revised programme under clause 32 against the Accepted Programme: the progress shown, its effect on the remaining work, how the Contractor plans to deal with delays and any other changes it proposes. The client gets a short report on planned Completion and any Key Dates.

PROTECT

Compensation event quotations

We check the delay in each quotation and any altered programme in it against the Accepted Programme that clause 63 says to use. Your reply under clause 62.3 then accepts the quotation, instructs a revised one with your reasons (clause 62.4) or notifies that you will make your own assessment.

PROTECT

Your own assessments

Where clause 64 says the Project Manager assesses a compensation event, we prepare the assessment of the delay and the programme evidence behind it, for you to issue in your name.

A quotation check from £950 + VAT · A programme review or a delay assessment from £1,250 + VAT · Monthly review from £1,400 a month + VAT

Monthly review covers each revised programme and a short report to the client. Three months, then 30 days' notice. Quotation checks and delay assessments are priced separately.

What a programme review looks like

Sample programme acceptance review on a demo project: four findings, each with its reason under clause 31.3 and wording for the Project Manager's reply

A sample on a demo project: each finding is tied to one of the four reasons in clause 31.3, with wording ready for your reply. All names and dates are fictional.

How we work

One side per project

We act for one side on a project. If we work for the Contractor on a job, we do not review for that job's Project Manager or client. The same holds the other way round.

Inside the two weeks

A programme review reaches you within 5 working days of the submission reaching us and a quotation check within 3. The sooner it reaches us, the more of the two weeks you keep for your reply. A late reply is itself a compensation event (clause 60.1(6)). A quotation is treated as accepted if the Contractor notifies the failure and you still have not replied two weeks later (clause 62.6). Under NEC4 a programme is too, after one further week (clause 31.3).

Your name on the reply

We advise. The reply, the reasons and any assessment go out from the Project Manager, in the Project Manager's name.

In confidence

We have done this work for the client's side before. None of those clients is named, here or anywhere else. Our reports go only to you and to those you choose.

Who leads the review

Roman Bazelchuk leads every review. He is an NEC Accredited Project Manager and holds APMG Project Planning and Control.

We know what an acceptable programme looks like: on one NEC3 job, every monthly revision we prepared was accepted for 18 months.

Questions Project Managers and clients ask us

Is this the real critical path?

We trace the critical path through the logic, the durations and the constraints. Then we show you where it really runs and what drives planned Completion.

Are there enough resources on the critical path?

For each operation, clause 31.2 asks for a statement of how the Contractor plans to do the work, with the principal Equipment and other resources. We check those resources against the durations on the critical path. A programme that does not represent the Contractor's plans realistically is one of the four reasons for not accepting it (clause 31.3).

Can the project finish earlier?

We show where the programme has room, in float, sequence or resources. The Contractor can plan to finish early by its own choice. Bringing the Completion Date forward is an acceleration under clause 36, which needs the Contractor's agreement. The Project Manager instructs a quotation for it. Accepting the quotation changes the Prices, the Completion Date and the Key Dates.

Have a programme or a quotation on your desk?

Tell us the contract and its Option, the date the submission arrived and when your reply is due.

You don't need to send anything first.