top of page
Planning advice for contractors
Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search
All Articles


Relevant Events vs compensation events: what JCT-trained teams get wrong
Vocabulary transfers faster than machinery. A JCT team learns to say compensation event within a fortnight, then prices its first one like an extension of time application with the money to follow. There is no money to follow. The mechanism comparison in full: what triggers each, who assesses it, against what standard, and why the notice reflex has now flipped on both contracts.

Roman Bazelchuk
5 days ago8 min read


JCT vs NEC: what actually changes for a contractor
Most JCT and NEC comparisons stop at philosophy: one allocates risk, the other encourages collaboration. Both true, and useless when the project manager has just rejected your programme. This is what actually changes when a team fluent in JCT runs an NEC job: the programme becomes a contractual instrument, extensions of time become compensation events on an eight-week clock, change is valued from Defined Cost rather than your rates, and early warnings acquire a price.

Roman Bazelchuk
Aug 248 min read


The NEC Compensation Event Quotation: How the Money Is Built
A compensation event quotation has two limbs, time and money, and the money is the one contractors price worst. This is the guide to the change to the Prices: how it is built from Defined Cost and the Fee under clause 63.1, why your tendered rates usually do not apply, where your overhead and profit actually sit, why the forecast you agree is final, and the handful of points where valid entitlement quietly leaks away in the pricing.

Roman Bazelchuk
Aug 2011 min read


NEC Programme Not Accepted: The Clause 31.3 Response Playbook
The notice says not accepted, and what happens next decides more than the fate of one submission. This playbook covers the moment in full: the four reasons Clause 31.3 permits and why they are the only four, the detail a notice must give you under Clause 13.4, the triage that sorts right from wrong from unclear, when withholding acceptance becomes a compensation event under 60.1(9), and the cost of drifting while the Accepted Programme goes stale.

Roman Bazelchuk
Aug 1610 min read


FIDIC Programme and EOT Evidence on EU-Funded Projects
FIDIC is the contract of EU-funded infrastructure, and the 2017 Edition decides extensions of time on the programme and the records behind it, not on the merits. On CEF-funded work those records also have to survive a funding audit. A guide for UK contractors moving into EU work and Baltic teams on funded jobs: what Sub-Clause 8.3 demands, how the 28-day and 84-day claim time bars work, and what an audit-ready FIDIC programme and claim actually contain.

Roman Bazelchuk
Jun 279 min read


Premier Modular v Maidstone: the NEC Accepted Programme lesson behind a £1.65m ruling
In June 2026 the High Court refused to enforce a £1.65m NEC adjudication award in Premier Modular v Maidstone and Tunbridge Wells NHS Trust. The legal headline is natural justice. The lesson for contractors is a project controls one. The whole dispute turned on which programme was the Accepted Programme, and the date the claim relied on was never in it. Under NEC, a compensation event is only as good as the Accepted Programme it stands on, and acceptance is a status you earn,

Roman Bazelchuk
Jun 216 min read


Hong Kong NEC4 ECC: Programme Compliance Under the 2023 Bespoke Edition
Hong Kong now runs more than 680 public works contracts on the NEC form and, since July 2023, has its own stand-alone edition of the ECC. The bespoke Hong Kong NEC4 ECC re-engineers payment timing, compensation event assessment and dispute resolution, and every change lands on the programme. This is what the 2023 edition changes at programme level, where first submissions fail acceptance, and what a defensible programme looks like.

Roman Bazelchuk
Jun 127 min read


What the project manager checks when reviewing your NEC programme
Most contractors prepare NEC programmes for submission. The strongest contractors prepare them for review. The difference is whether the planning team knows what the project manager actually checks, in what order, and what triggers rejection at each step. This article walks through the review sequence as the project manager experiences it: the first thirty seconds, the structural integrity pass, the clause 31.2 information check, the realism test, and the scope compliance che

Roman Bazelchuk
Jun 119 min read


How to structure a time impact assessment under NEC4
Most NEC4 time impact assessments fail at the project manager's desk, not in the planning team. The analysis is usually sound. The structure is what fails. This article explains the five elements every accepted assessment contains: the dividing date with justification, the accepted programme with version, the compensation event fragnet built in isolation, the impacted programme with the calculation, and the narrative that walks the project manager through the cause and effect

Roman Bazelchuk
May 2520 min read
bottom of page
