top of page
Planning advice for contractors
Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search
All Articles


FIDIC Programme and EOT Evidence on EU-Funded Projects
FIDIC is the contract of EU-funded infrastructure, and the 2017 Edition decides extensions of time on the programme and the records behind it, not on the merits. On CEF-funded work those records also have to survive a funding audit. A guide for UK contractors moving into EU work and Baltic teams on funded jobs: what Sub-Clause 8.3 demands, how the 28-day and 84-day claim time bars work, and what an audit-ready FIDIC programme and claim actually contain.

Roman Bazelchuk
Jun 279 min read


Premier Modular v Maidstone: the NEC Accepted Programme lesson behind a ÂŁ1.65m ruling
In June 2026 the High Court refused to enforce a ÂŁ1.65m NEC adjudication award in Premier Modular v Maidstone and Tunbridge Wells NHS Trust. The legal headline is natural justice. The lesson for contractors is a project controls one. The whole dispute turned on which programme was the Accepted Programme, and the date the claim relied on was never in it. Under NEC, a compensation event is only as good as the Accepted Programme it stands on, and acceptance is a status you earn,

Roman Bazelchuk
Jun 216 min read


Hong Kong NEC4 ECC: Programme Compliance Under the 2023 Bespoke Edition
Hong Kong now runs more than 680 public works contracts on the NEC form and, since July 2023, has its own stand-alone edition of the ECC. The bespoke Hong Kong NEC4 ECC re-engineers payment timing, compensation event assessment and dispute resolution, and every change lands on the programme. This is what the 2023 edition changes at programme level, where first submissions fail acceptance, and what a defensible programme looks like.

Roman Bazelchuk
Jun 127 min read


What the project manager checks when reviewing your NEC programme
Most contractors prepare NEC programmes for submission. The strongest contractors prepare them for review. The difference is whether the planning team knows what the project manager actually checks, in what order, and what triggers rejection at each step. This article walks through the review sequence as the project manager experiences it: the first thirty seconds, the structural integrity pass, the clause 31.2 information check, the realism test, and the scope compliance che

Roman Bazelchuk
Jun 119 min read


How to structure a time impact assessment under NEC4
Most NEC4 time impact assessments fail at the project manager's desk, not in the planning team. The analysis is usually sound. The structure is what fails. This article explains the five elements every accepted assessment contains: the dividing date with justification, the accepted programme with version, the compensation event fragnet built in isolation, the impacted programme with the calculation, and the narrative that walks the project manager through the cause and effect

Roman Bazelchuk
May 2520 min read


NEC programme acceleration and mitigation: the practical contractor guide
NEC requires mitigation but cannot impose acceleration. Most contractors confuse the two. Contractors who mitigate when they should be quoting for acceleration give away recovery work the contract entitles them to be paid for. Contractors who refuse to mitigate lose entitlement because the assessment assumes they would have mitigated anyway. This is the practical guide to understanding where the line sits and how to protect the commercial position on both sides of it.

Roman Bazelchuk
May 1816 min read


5 signs your project programme has lost integrity
A programme that has lost integrity does not announce itself. It looks exactly like one that works. The problems only surface when a compensation event tests it and the programme cannot answer the one question the NEC contract keeps asking. This article describes five signs any project director can check in ten minutes, without specialist planning knowledge, to know whether the programme is protecting their commercial position or quietly giving it away.

Roman Bazelchuk
May 1113 min read


What a clause 32 programme revision actually needs to show under NEC
Most contractors submit programme revisions that update progress, move the data date forward, and miss everything else clause 32 requires. The project manager receives a schedule that shows where the job is but not what the contractor is doing about it. That is not a revision. It is a progress snapshot. This article explains what a clause 32 programme revision actually needs to contain, why most revisions are rejected, and what to do when the project manager is deliberately a

Roman Bazelchuk
May 419 min read


Primavera P6 for NEC programmes: The Complete Contractor Guide
Primavera P6 is the industry-standard scheduling tool on major UK construction projects. It is also an opinionated one. Its defaults were shaped by contracts that work very differently from NEC, and a P6 schedule built to generic best practice will usually look fine on the surface and fail at the moments that matter most. This is the complete contractor guide to Primavera P6 for NEC programmes.

Roman Bazelchuk
Apr 2720 min read
bottom of page
