top of page

Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search
Programme Best Practice
Practical guidance on programme structure, updates, accepted programmes, logic, progress recording and good planning discipline on live projects.


5 signs your project programme has lost integrity
A programme that has lost integrity does not announce itself. It looks exactly like one that works. The problems only surface when a compensation event tests it and the programme cannot answer the one question the NEC contract keeps asking. This article describes five signs any project director can check in ten minutes, without specialist planning knowledge, to know whether the programme is protecting their commercial position or quietly giving it away.

Roman Bazelchuk
2 days ago13 min read


What a clause 32 programme revision actually needs to show under NEC
Most contractors submit programme revisions that update progress, move the data date forward, and miss everything else clause 32 requires. The project manager receives a schedule that shows where the job is but not what the contractor is doing about it. That is not a revision. It is a progress snapshot. This article explains what a clause 32 programme revision actually needs to contain, why most revisions are rejected, and what to do when the project manager is deliberately a

Roman Bazelchuk
May 419 min read


Primavera P6 for NEC programmes: The Complete Contractor Guide
Primavera P6 is the industry-standard scheduling tool on major UK construction projects. It is also an opinionated one. Its defaults were shaped by contracts that work very differently from NEC, and a P6 schedule built to generic best practice will usually look fine on the surface and fail at the moments that matter most. This is the complete contractor guide to Primavera P6 for NEC programmes.

Roman Bazelchuk
Apr 2720 min read


NEC Clause 31 Programme Acceptance: The Complete Guide For Contractors
Most contractors treat clause 31 as a procedural hurdle to clear at the start of the job. Submit the programme, wait for acceptance, move on. That approach quietly hands commercial control to the project manager. This article explains what the accepted programme actually protects, how the deemed acceptance mechanism works, and why a programme that was accepted at mobilisation provides almost no commercial protection by month six.

Roman Bazelchuk
Apr 1815 min read


When an Accepted Programme Stops Protecting a Specialist Contractor Under NEC
For mechanical, electrical, civil, groundworks and fit-out contractors, the accepted programme often only becomes important when change or delay lands on a programme that no longer reflects the live job. This article explains why that drift matters under NEC and how programme protection is often lost by degrees, not all at once.

Roman Bazelchuk
Mar 307 min read


How Specialist Subcontractors Should Manage Programme Updates Under NEC Without a Full Planning Team
Many specialist subcontractors run NEC packages without a full planning team. The issue is not team size. It is whether the programme stays live, current and commercially usable while the job is moving.

Roman Bazelchuk
Mar 248 min read


Time Risk Allowance vs Terminal Float in NEC: Why Contractors Need to Keep the Difference Clear
Time Risk Allowance and terminal float both create breathing space in an NEC programme. That is why contractors often confuse them. But they sit in different places, serve different purposes, and blurring the line between them weakens programme acceptance, distorts the update cycle, and makes compensation event assessments harder to defend. This article explains what each one actually is, how they connect without being the same, and why keeping the distinction clean matters c

Roman Bazelchuk
Mar 127 min read


NEC Clause 15 Early Warnings: A Quantified Register That Reduces Delay
Clause 15 only works when early warnings trigger decisions and programme movement. Here’s a quantified register method and weekly rhythm you can run on real jobs.

Roman Bazelchuk
Mar 96 min read


Pre-Construction Planning for Contractors: The Practical Programme and Project Controls Guide (Civils, Mechanical and Electrical)
For contractors, pre-construction planning is not “getting ready to start”. It is building a credible, auditable delivery plan and the control system you will use to manage progress and change.

Roman Bazelchuk
Jan 225 min read


7 Common Pitfalls When Contractors Use Excel Programmes on NEC Jobs
Excel is great for registers and dashboards, but risky as the master NEC programme. Here are 7 pitfalls that undermine cause and effect, plus fixes using a lean logic linked schedule.

Roman Bazelchuk
Jan 144 min read


Construction planning that wins work and survives the reality of delivery
The programme used to sit alongside the job. Now it often reveals whether the job is really under control. This article explains why construction planning has become a more serious commercial function, and why the firms that maintain a believable live time position are starting to separate themselves from those that reconstruct one later.

Roman Bazelchuk
Dec 26, 20258 min read


NEC vs FIDIC
Practical Differences for Contractors on Programme, Reporting and Compensation Events For contractors delivering engineering and construction projects in the UK and internationally, the choice between NEC and FIDIC isn’t just a legal technicality – it changes how you plan, report and secure entitlement to time and money. Programme requirements, reporting expectations and the way changes are valued all work differently under each form. If you treat them the same, you increase

Roman Bazelchuk
Dec 5, 20256 min read


Unlocking Cashflow Through NEC4 Construction Schedules
Why Cashflow Now Lives Inside the Programme Cashflow remains one of the defining determinants of contractor survival. Multiple studies identify poor cashflow forecasting and weak financial planning as major contributors to contractor insolvency—even on technically successful projects (Ejaz & Nawaz, 2020). As construction projects become more complex and financially constrained, researchers emphasise the need for integrating real project data into cashflow modelling rather tha

Roman Bazelchuk
Nov 29, 20256 min read


5 Time Risk Allowance Mistakes That Undermine NEC Programme Acceptance
Time Risk Allowances are not padding. Under NEC, they are part of realistic planning. Clause 31.2 requires the contractor’s programme to show float and time risk allowances, and the NEC guidance is clear that where reasonable TRA is missing, unclear or not shown properly, the Project Manager has grounds not to accept the programme because it does not represent the contractor’s plans realistically or does not show the information the contract requires. That sounds technical, b

Roman Bazelchuk
Aug 28, 20256 min read


NEC4 delivery for subcontractors: how specialist contractors excel on live projects
A practical guide to NEC4 delivery for subcontractors: build accepted programmes, run early warnings properly, manage compensation events to timescales, and keep evidence audit-ready.

Roman Bazelchuk
Jul 20, 20254 min read


Why M&E contractors lose commercial protection early under NEC
On NEC, M&E margin is often lost in the silent gap between a builder's delay and a contractor's commissioning window.

Roman Bazelchuk
Jun 9, 20256 min read
bottom of page