top of page
NEC programme control guides
How to get a programme accepted under clause 31, keep it accepted through clause 32 revisions and use it to protect time and money. Written for planners and project managers running live NEC jobs.
Search


The NEC4 contract explained: how the ECC works, from the programme side
The NEC4 contract read from the planning desk: how the ECC is put together, the main and secondary options in a table each and who does what. Then how time, money and change run back to the Accepted Programme, with one late access event worked through week by week.
Oct 2623 min read


NEC clause 31 programme acceptance: the complete guide for contractors
Most contractors treat clause 31 as a procedural hurdle to clear at the start of the job. Submit the programme, wait for acceptance, move on. That approach quietly hands commercial control to the project manager. This article explains what the accepted programme actually protects, how the deemed acceptance mechanism works, and why a programme that was accepted at mobilisation provides almost no commercial protection by month six.
Apr 1817 min read


DCMA 14-point assessment for NEC programmes: what each check means for acceptance
Many programmes now arrive with DCMA scorecards attached or come back with them in the reply. This guide reads all fourteen checks against the four reasons clause 31.3 gives for not accepting an NEC4 programme, explains why a score alone is not one of them, shows how to run the checks in Primavera P6 and how the Scope can make them contractual. It comes with a DCMA 14-point checklist to download.
2 days ago14 min read


MS Project to Primavera P6: what to do when the contract requires P6
The contract is signed, the Scope or Specification says the programme goes in as Primavera P6, and the tender programme was built in MS Project. An export produces a file, not a programme the client's planner will accept. This guide covers where NEC4, JCT and FIDIC put the software requirement and the first programme's deadline, what an import from MS Project keeps and loses, whether to convert or rebuild, and how to set the P6 programme up for the contract.
Nov 516 min read


Delay analysis methods: what each one needs from your programme
The SCL Protocol lists six delay analysis methods and the commentary argues endlessly about which is best. The question is usually settled already. What your programme contains and what records survive decide which methods are open to you, and on an NEC contract clause 63.5 has prescribed one before the argument starts.
Nov 28 min read


NEC4 payment applications: what to submit, what gets certified and when you are paid
Under NEC4 the assessment date arrives whatever has been filed, and a month without an application is a month without an increase. This guide walks the payment clauses from the contractor's side: what the application must show on each main Option, the certificate and interest, pay less notices under Y(UK)2, how the programme controls the cash, and the clause 53 final assessment. With a two-page Payment Application Checklist.
Oct 2914 min read


FIDIC 1999 vs 2017: Clause Mapping for Programme and Claims
Most of what changed between the 1999 and 2017 FIDIC conditions is a clause number. The problem is the templates that were never updated: on a 2017 contract, a notice citing Sub-Clause 8.4 for an extension of time is citing the advance warning provision instead.
Oct 198 min read


NEC4 options A to F: how each main option pays and what it asks of the programme
NEC4 has six main options, and the one in the contract decides how the Contractor is paid, who carries an overrun and what the programme is asked to support. This guide takes them in pairs: the priced contracts A and B, the target contracts C and D, and the cost reimbursable contracts E and F. For each, what an assessment pays, where the cost risk sits, which clauses only that option carries, and what the planner has to keep current for the money to hold up.
Oct 1617 min read


A programme of works the site can follow and the contract can rely on
Most contracts ask for a programme of works, and many of the ones that reach a client are bars drawn without logic. This guide sets out what a construction programme must show, the types a project runs through from tender to as-built, how to read one in six checks, and what JCT, NEC4 and FIDIC ask of it, with a fixed price for having yours built in P6.
Oct 1214 min read


Programme Recovery: When Working Harder Stops Working
The client asks for a recovery plan. Somebody compresses the bars until the end date fits and issues it. That document is not a recovery plan, it is the same programme with less air in it, and everyone knows it within a fortnight.
Oct 28 min read


Monthly construction progress reports: why they arrive too late
Data cut-off on the 25th, report issued around the 5th, discussed mid-month. A decision taken on the 15th rests on information that was already three weeks old when it was read. Nobody is hiding anything. The loop is simply longer than the rate at which the job changes.
Sep 287 min read


NEC Programme Not Accepted: The Clause 31.3 Response Playbook
The notice says not accepted, and what happens next decides more than the fate of one submission. This playbook covers the moment in full: the four reasons Clause 31.3 permits and why they are the only four, the detail a notice must give you under Clause 13.4, the triage that sorts right from wrong from unclear, when withholding acceptance becomes a compensation event under 60.1(9), and the cost of drifting while the Accepted Programme goes stale.
Aug 1610 min read
Need help on a live NEC job?
The guides explain the rules. On a 30-minute call we talk through your programme, notice or quotation and what to do next. The call is confidential and you don't need to send anything first.
Scope confirmed before billing
bottom of page