7 Common NEC Programme Traps for M&E Contractors
- Roman Bazelchuk
- Jun 9, 2025
- 6 min read
Updated: 10 hours ago

If you are an M&E contractor working under an NEC contract, you will already know the line people repeat on every job: “If it’s not on the programme, it doesn’t exist.” On NEC projects that is not just a planning cliché. The programme becomes the working record of what you said you would do, when you said you would do it, and how change and delay should be assessed against that plan.
When disputes do happen, adjudication remains a heavily used route in the UK and the volume of referrals has been reported at record levels in recent reporting periods, so weak programme administration is a real commercial exposure, not just an admin problem.
For M&E specialists, the risk is amplified. Your scope often sits on the critical interface between design, procurement and access, with commissioning and handover obligations that are unforgiving. A programme that is “good enough for a look-ahead” is rarely good enough for NEC acceptance, forecasting, or entitlement.
Below are the 7 common NEC Programme trapsfor M&E contractors we repeatedly see on live M&E NEC projects, and the practical fixes that help you get accepted, stay credible, and protect margin.
Why NEC M&E programmes get rejected
Under NEC, the Project Manager is required to respond to a submitted programme within the contract timescales, and the reasons for not accepting are constrained. In practice, M&E programmes are commonly not accepted because they do not reflect a practicable plan, do not include the information the contract requires, or do not represent the contractor’s true plan realistically.
When acceptance slips, the knock-on is bigger than people expect: it becomes harder to agree progress narratives, harder to demonstrate the time effect of change, and easier for conversations to drift into opinion. NEC is designed to keep things prospective and auditable. A weak programme pushes you into hindsight and argument.
Trap #1: The programme is too high-level to be “assessable”
What it looks like:
You submit a neat bar chart with “Design”, “Procurement”, “Install”, “Test & Commission”, and “Handover” as single lines. It might be fine for an internal overview, but it is not traceable. The missing detail is exactly where M&E delay risk lives: submittals, approvals, long-lead equipment, builders work, energisation, IST, witness testing, BMS integration, pressure testing, flushing, validation, and client access.
Fix it:
Break your scope into a logic-linked, assessable structure that mirrors how you actually deliver. A good rule for NEC is: if an event can change time or cost, it needs a visible place in the programme.
Trap #2: Missing access and constraint logic
What it looks like:
The programme assumes you can start everywhere on day one, progress flows without stoppages, and ceilings close neatly when you want them to. Real sites do not work like that, especially in refurbishment, live environments, or multi-trade fit out.
Fix it:
Turn constraints into explicit logic. If access dates are stated in the contract, include them. If access is created by other trades, show the predecessor. If your work creates access for others, show that too. NEC programmes get stronger when they show real dependencies, not just desired dates.
Trap #3: Unrealistic calendars, progress rules, and “hidden acceleration”
What it looks like:
Everything is set to a generic 5-day week, even though you are working weekends, nights, or out-of-hours shutdown windows. Or the opposite: you promise a 6-day calendar that your labour plan cannot support. Another common issue is progress being updated inconsistently, with out-of-sequence work masking what is actually driving completion.
Fix it:
Match the calendar to the delivery plan you can resource and supervise. If you are planning weekend working, show it, and ensure it is credible. Set consistent progress rules and keep them stable. If you need to recover time, show recovery explicitly as a change in logic/resource approach, not as an invisible assumption.
On NEC jobs, credibility matters as much as logic. A programme that “always looks fine” is often the one that fails when scrutinised.
Trap #4: Treating programme acceptance as passive admin
What it looks like:
Programmes get submitted, then everyone waits. The Project Manager rejects, you resubmit, and the cycle repeats. Meanwhile the live job moves on and the “accepted” programme becomes stale.
Fix it:
Manage acceptance proactively like a commercial process. NEC sets expectations around response and reasons. If the Project Manager does not respond within the allowed period, NEC4 provides a mechanism where the contractor can notify the failure and, if the failure continues, the programme can be treated as accepted.
Practically, the best results come from a structured submission pack:
A one-page compliance checklist; a revision log; a short programme narrative explaining what changed and why; and a short acceptance workshop with the Project Manager and key stakeholders. This reduces “admin rejection” and forces issues into the open early.
Trap #5: Not revising the programme properly
What it looks like:
The programme is updated only when someone shouts, or only when a payment assessment is due. CEs, early warnings, client changes, delayed information, design development and procurement slippage exist in emails and meetings but not in the programme.
Fix it:
Treat the monthly update as a non-negotiable control cycle. NEC’s intent is an up-to-date, realistic and practicable programme that includes the forecast effect of known delays and changes, not a historic record.
A simple routine that works on M&E jobs:
Cut-off and progress date agreed.
Progress inputs captured (area-based, not just percent complete).
Logic reviewed for upcoming 4-8 weeks.
Forecast completion recalculated, then explained.
Narrative issued that ties the change back to facts (RFIs, approvals, access, deliveries, testing results).
Trap #6: Compensation Events are notified, but the time impact is not demonstrated
What it looks like:
You notify a CE, but the programme never shows the effect. Or you issue a narrative without a logic-linked “before and after” that an NEC PM can accept and audit. The outcome is predictable: the CE is treated as cost-only, or the time effect is dismissed as unproven.
Fix it:
Every CE that has a time effect needs programme evidence. Keep it practical and prospective. Build a simple, repeatable method your team can execute under pressure:Use the accepted programme at the appropriate dividing date as your reference; insert the change as a logic-linked fragnet; show what it drives (key dates, sectional completion, access, energisation, commissioning), and issue a short narrative that explains the mechanism of delay in plain English.
For M&E, the most common missed drivers are not “install duration”. They are late approvals, long-lead procurement slips, access restrictions, energisation windows, integrated testing readiness, and witness hold points.
Trap #7: Interfaces are not owned
What it looks like:
The programme shows your installation, but not the enabling works. Builders work openings, plinths, containment routes, ceiling coordination, power-on, water-on, drainage connections, fire stopping release, insulation access, and commissioning prerequisites are assumed.
Fix it:
Make interfaces visible and assign ownership through logic. If something is an Employer risk, show it as an activity (or a milestone) with the right predecessor/successor relationships so its impact is assessable. If it is your risk, show it clearly so your team can manage it.
What “good” looks like for an M&E NEC programme
An acceptance-ready NEC programme for M&E typically has these characteristics:
It is logic-linked and shows a practicable sequence by area and system (not just by trade).It includes design, approvals, procurement, offsite activities, testing, commissioning, and handover, not only site installation.It clearly shows key dates, access dates and constraints, and it is updated to reflect actual progress and realistic forecasts.It includes a short narrative and a revision log so the Project Manager can see what changed and why.It is managed as a live control system, not a monthly PDF exercise.
NEC’s own guidance and industry commentary repeatedly emphasise the value of an up-to-date accepted programme as a core management tool, not paperwork.
A practical checklist you can apply before every submission
Does the programme include the contract-required information (key dates, access dates, completion, realistic sequence)?
Are design, approvals, procurement and offsite works visible and logic-linked?
Are constraints and access releases shown as activities/milestones with predecessors?
Do calendars reflect real working (and are they credible)?
Is progress updated consistently (and can you explain any out-of-sequence work)?
Are early warnings and known delays reflected as forecast changes?
Are CEs shown with logic-linked evidence, not narrative only?
Are interfaces explicit, with ownership visible in the logic?
Are long-lead items modelled end-to-end, including approvals and FAT?
Does the narrative explain what changed and what it means for the completion forecast?
Can a third party audit the logic and reach the same conclusion?
If the PM rejects, do you have a structured route to correct and resubmit quickly?
Final word
Most M&E contractors do not lose entitlement because they “did not do the work”. They lose it because they cannot demonstrate the mechanism of delay credibly, using the programme the contract expects.
If you want a second pair of eyes, the fastest support we typically provide is a programme health check (acceptance readiness, logic, constraints, CE integration, and a simple monthly update routine your team can run). Director-led QA makes the difference here because small technical issues become big commercial ones on NEC.




Insightful article