PROJECT CASE STUDY

Northwich Carbon
Capture Plant

  • Civil infrastructure · Full delivery cycle

Planning and project controls support on a £20M carbon capture facility, maintaining programme integrity through evolving design, civil infrastructure complexity and multi-trade interfaces.

CLIENT

Studley Engineering

PROJECT VALUE

£20M

LOCATION

Northwich, England

SECTOR

Carbon Capture & Storage

CONTRACT

FIDIC

THE CHALLENGE

Keeping a live baseline credible while the design was still moving

This project combined civil infrastructure, process engineering and an evolving main contractor design. The planning challenge was to maintain a baseline credible enough for commercial reporting and client submissions, while remaining responsive to design change without losing logic integrity or critical path credibility.

​

The scope involved integrating multiple specialist trades into a master schedule, each with their own procurement lead times, site access dependencies and sequencing requirements. Managing the change register alongside a live programme, while maintaining a credible critical path for stakeholder reporting, was the core planning task throughout the project.

​

This support gave the project team a maintained baseline, live change visibility and a consistent reporting structure throughout a delivery phase where the design and scope were moving continuously.

PROJECT FACTS

Value

Type

Location

Client

Project type

Delivery

£20M

CCS Facility

Northwich

Studley Engineering

Civil infrastructure

Remote & site

WHAT WAS DELIVERED

Planning and controls support across the full delivery cycle

PROGRAMME BASELINE

First-principles baseline schedule

Logic-linked baseline programme built from first principles, aligned to the agreed contract dates and structured to support commercial programme management throughout delivery.

CHANGE MANAGEMENT

Live change control alongside the programme

Maintained a structured change register to track and quantify the programme impact of design changes as the main contractor's requirements evolved, keeping the commercial position visible alongside the live schedule.

MULTI-TRADE INTEGRATION

Subcontractor schedule integration

Integrated subcontractor schedules into the master programme, with procurement schedules developed and maintained to give clear visibility of long-lead items and trade sequencing dependencies.

PHASED PLANNING

Detailed phased plans

Developed phased plans to manage the sequencing of subsequent trades, ensuring smooth integration and clear interface management as the project moved between construction stages.

GOVERNANCE

Planning and programme outputs on this project were issued under NEC-accredited governance.

​

About our credentials ›

PERFORMANCE MONITORING

Earned value analysis

Applied earned value analysis to provide an objective, data-led view of programme performance, giving the project team and client a consistent basis for progress reporting and forecasting.

REPORTING

Stakeholder reporting and submission support

Regular programme submissions and weekly progress reporting tailored to a wide range of project stakeholders, covering programme narratives, timeline visualisations and attendance at client and internal meetings.

WHAT THIS DELIVERED

Accepted baseline maintained through continuous design change

BASELINE CREDIBILITY

01

A logic-linked baseline remained commercially defensible throughout the project despite ongoing scope and design evolution, giving the contractor a reliable reference point for programme reporting and client submissions at every stage.

Commercial exposure visible in real time alongside the live programme

CHANGE CONTROL

02

A maintained change register kept the cumulative programme impact of design changes quantified and traceable throughout delivery, protecting the contractor's commercial position at each reporting cycle

Subcontractor sequences integrated without disruption to the master schedule

MULTI-TRADE INTEGRATION

03

Procurement schedules and phased plans kept trade sequencing visible and coordinated, reducing interface risk and giving the project team clear sight of long-lead dependencies before they became programme issues.

Consistent stakeholder reporting maintained from baseline to completion

REPORTING DISCIPLINE

04

Regular programme submissions, earned value analysis and progress narratives gave both the contractor and client team a consistent, data-led view of project performance throughout a delivery phase where scope was moving continuously.

Need planning support on a complex live project?

We support contractors and asset owners on complex civil, energy and industrial projects. Tell us your project stage and we'll confirm how we can help.

Confidential review · Scope confirmed before chargeable work begins

bottom of page