PROJECT CASE STUDY

Chemical Processing Plant
Major Shutdown & Capacity Upgrade

  • Process industry shutdown · Full-time on-site delivery

Full project controls support for a major shutdown and capacity upgrade at a specialist chemical manufacturing facility, coordinating multiple contractors, integrating disconnected source schedules and maintaining live programme discipline under shutdown conditions.

CLIENT

Studley Engineering

PROJECT VALUE

£5M

LOCATION

Fleetwood, England

SECTOR

Chemical Processing

CONTRACT

JCT

THE CHALLENGE

Zero tolerance for drift: coordinating a live shutdown with contractors running to different schedules

Shutdown projects at chemical processing facilities carry a specific commercial pressure: every day offline is a day of lost production for the client. That means programme slippage is not an abstract risk, it has an immediate, quantifiable cost. The planning challenge on this project was compounded by the fact that contractors and subcontractors arrived with their own schedules in different formats (Excel, MS Project), with no single integrated view of the shutdown sequence.

​

Establishing a coherent Primavera P6 master programme from those disconnected sources, and making the critical path and key commissioning deliverables visible to the engineering team before work began, was the prerequisite for everything else: progress tracking, change management, earned value and safe execution of subsequent trades.

​

This project gave the team a maintained master schedule, live change visibility and consistent performance reporting throughout a pressurised shutdown delivery phase.

PROJECT DETAILS

Planning software

Source integration

Delivery model

Update cadence

Performance monitoring

Project type

Primavera P6

Excel & MS Project → P6

Full-time on-site

Weekly

Earned value analysis

Shutdown & upgrade

WHAT WE DELIVERED

Planning and controls support across the full shutdown

PROGRAMME INTEGRATION

P6 master schedule from multiple sources

Built a construction-oriented master programme in Primavera P6, integrating existing plans and third-party schedules from Excel and MS Project, giving the project team a single, coherent view of the shutdown sequence for the first time.

ON-SITE DELIVERY

Full-time dedicated on-site planner

A dedicated planner embedded on site throughout the shutdown, enabling real-time progress capture, direct engagement with the engineering division and immediate response to programme pressure as it developed.

COMMISSIONING CONTROL

Key deliverables tracker for commissioning

Integrated a key deliverables tracker into the master programme, making critical commissioning milestones visible and actively tracked, so the engineering team could plan subsequent activities with confidence.

CHANGE MANAGEMENT

Live change register alongside the programme

Maintained a detailed change register tracking the impact of evolving contractor designs and requirements on the programme, keeping the commercial position visible as the scope changed through delivery.

GOVERNANCE

Planning and programme outputs on this project were issued under NEC-accredited governance.

​

About our credentials ›

PERFORMANCE MONITORING

Earned value analysis and dashboard

Applied earned value analysis to provide an objective basis for progress and budget reporting. Timeline visualisation and project metrics dashboard gave senior stakeholders a consistent, data-led view for decision-making at each project stage.

COMPENSATION EVENTS

CE claims management and verification

Supported management, coordination and verification of compensation event claims, maintaining traceable programme records and ensuring change impacts were correctly evidenced and assessed throughout delivery.

WHAT THIS DELIVERED

One coherent master schedule from disconnected contractor sources

PROGRAMME CONTROL

01

Multiple contractor schedules from different platforms unified into a single P6 master programme, giving the team a reliable view of the shutdown sequence from the outset.

Engineering team could manage construction activities safely and with confidence

CRITICAL PATH VISIBILITY

02

Critical deliverables and commissioning milestones made visible to the engineering division before work began, reducing ambiguity during a high-pressure shutdown environment.

Design and scope changes tracked live against the master programme

CHANGE VISIBILITY

03

The change register ran alongside the live schedule, so programme impacts of evolving contractor requirements were captured in real time, not reconstructed under time pressure.

Consistent, data-led reporting across all project stakeholders

STAKEHOLDER REPORTING

04

Weekly progress reporting, earned value analysis and a project metrics dashboard gave client, management and contractor teams a consistent, objective basis for decision-making throughout delivery.

Need planning support on a shutdown or industrial project?

We support contractors and asset owners on complex civil, energy and industrial projects. Tell us your project stage and we'll confirm how we can help.

Confidential review · Scope confirmed before chargeable work begins

bottom of page