top of page
Planning advice for contractors
Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search
All Articles


NEC3 vs NEC4: the changes that matter for contractors' programmes and project controls
A practical NEC3 vs NEC4 comparison focused on programme acceptance, treated acceptance, early warning discipline and CE integration, based on NEC’s “Next Generation” white paper.

Roman Bazelchuk
Mar 516 min read


NEC4 compensation events: when the project manager can make their own assessment (clause 64) and how contractors protect entitlement
Clause 64 is not a procedural fallback. It is the contract's switching mechanism for commercial control of valuation. When the contractor submits compliant quotations on time with current programme information, the contractor controls valuation. When the contractor fails to meet any of the four conditions, the contract switches that control to the project manager, with consequences that typically reduce entitlement by thirty to sixty percent.

Roman Bazelchuk
Mar 320 min read


NEC4 compensation event time bar and the CE clock: clauses 61 and 62 explained
The NEC4 compensation event time bar is the most asymmetric provision in the entire contract. Almost every other NEC provision creates a spectrum of outcomes through judgement, extension mechanisms, or proportionate consequences. The eight-week time bar creates a cliff: notifications inside the period preserve entitlement, notifications outside it forfeit it entirely. The contractor who understands this asymmetry organises their administration around it.

Roman Bazelchuk
Feb 2519 min read


NEC4 compensation events without an accepted programme: how contractors protect entitlement when the baseline is missing
An accepted programme is not a procedural document. It is the shared reference frame against which every compensation event is assessed, every delay analysed, every progress conversation grounded. When it is missing, the reference frame itself becomes contested, and that contest favours the project manager. This is what the absence of an accepted programme actually means commercially, why it shifts control, and how contractors recover the position before the damage compounds.

Roman Bazelchuk
Feb 2016 min read


NEC4 compensation events: how to get quotations agreed and what makes them acceptable to the project manager
Most contractors ask how to get NEC4 compensation event quotations agreed. The question is the wrong one. The strongest contractors ask what makes a quotation acceptable to a project manager who wants to accept it and what makes a quotation rejectable by a project manager looking for reasons to reject. The first optimises for completeness. The second optimises for acceptability. The two are not the same.

Roman Bazelchuk
Feb 1017 min read


Managing subcontractor delay under NEC4: why every supply chain slip is two delays at once
Every subcontractor delay on an NEC4 project is two delays at once. The subcontract event runs on its own clock with its own notification requirements, evidence, and commercial outcomes. The head contract event runs on a parallel clock with its own clause 61.3 window, its own assessment, and its own clause 64 vulnerability. Most contractors run one of these processes diligently and the other partially or not at all.

Roman Bazelchuk
Feb 314 min read


How to score higher on Social Value in UK construction tenders
Evaluators have seen thousands of Social Value statements. The difference between a low score and a high one is rarely intent — it is evidence, deliverability, and a clear audit trail. This article explains what PPN 002 and the Social Value Model actually require, why most tender answers still fall short, and what a contract-linked jobs-and-skills commitment looks like when it stands up to post-award scrutiny.

Roman Bazelchuk
Jan 2910 min read


Pre-construction planning for contractors: the practical guide to designing the system before you run it
There is a four-to-twelve-week window between contract award and site mobilisation that the contractor's commercial outturn depends on more than any other stage of delivery. It is unremarkable in most calendars and rarely discussed at board level. Yet what gets set up during this window will determine, more than any subsequent decision, whether the project's commercial position is defensible at month eighteen. Pre-construction is not preparation.

Roman Bazelchuk
Jan 2217 min read


How UK contractors win NEC tender bids in 2026: what you are really being scored on
Under the Procurement Act 2023, the question contracting authorities are asking when they evaluate bids has changed. They are not asking "can you deliver this competitively." They are asking "can this selection be defended through the contract life under the published transparency regime." The two questions sound similar. They are not. This is the complete analysis of how UK contractors win NEC tenders in 2026: what changed on 24 February 2025.

Roman Bazelchuk
Jan 1924 min read
bottom of page
