top of page
Practical NEC guidance for contractors
Guides to NEC4 programmes, compensation events, payment and tender planning, written by an NEC Accredited Project Manager for Tier 1 and Tier 2 contractors. The first three are the best place to start.
Search


The NEC4 contract explained: how the ECC works, from the programme side
The NEC4 contract read from the planning desk: how the ECC is put together, the main and secondary options in a table each and who does what. Then how time, money and change run back to the Accepted Programme, with one late access event worked through week by week.
Oct 2623 min read


NEC clause 31 programme acceptance: the complete guide for contractors
Most contractors treat clause 31 as a procedural hurdle to clear at the start of the job. Submit the programme, wait for acceptance, move on. That approach quietly hands commercial control to the project manager. This article explains what the accepted programme actually protects, how the deemed acceptance mechanism works, and why a programme that was accepted at mobilisation provides almost no commercial protection by month six.
Apr 1817 min read


7 ways contractors lose entitlement on NEC4 compensation events
Every contractor running an NEC4 contract loses some compensation event entitlement that the contract would otherwise have delivered. The amount lost is not random. It is the predictable consequence of seven specific failure modes that recur across contractor types, contract sizes and sectors. Each is preventable through operational discipline.
Sep 4, 202519 min read


Delay analysis methods: what each one needs from your programme
The SCL Protocol lists six delay analysis methods and the commentary argues endlessly about which is best. The question is usually settled already. What your programme contains and what records survive decide which methods are open to you, and on an NEC contract clause 63.5 has prescribed one before the argument starts.
Nov 28 min read


Programme evidence in NEC claims and adjudication: what a planner adds
In an NEC time dispute the lawyers argue entitlement, but much of what decides it sits in the programme record: which programme the contract recognised at each dividing date, what happened against it and what each event did to planned Completion. This guide sets out what counts as programme evidence under NEC4, what a planner adds to a claim, what changes in an adjudication timetable and where the evidence tends to fail.
Oct 2212 min read


FIDIC 1999 vs 2017: Clause Mapping for Programme and Claims
Most of what changed between the 1999 and 2017 FIDIC conditions is a clause number. The problem is the templates that were never updated: on a 2017 contract, a notice citing Sub-Clause 8.4 for an extension of time is citing the advance warning provision instead.
Oct 198 min read


A programme of works the site can follow and the contract can rely on
Most contracts ask for a programme of works, and many of the ones that reach a client are bars drawn without logic. This guide sets out what a construction programme must show, the types a project runs through from tender to as-built, how to read one in six checks, and what JCT, NEC4 and FIDIC ask of it, with a fixed price for having yours built in P6.
Oct 1214 min read


Pre-construction services agreement (PCSA): key contractor obligations
A PCSA, or pre-construction services agreement, pays a contractor for defined services before the main contract is awarded. Law firms cover its scope, fees and termination. This guide covers the contractor's obligations from the planner's side: the programme built under it, the standard forms from JCT and NEC4, Option X22, the three routes for that programme at contract award under NEC4, and what to write into the services schedule before signing.
Oct 814 min read


Programme Recovery: When Working Harder Stops Working
The client asks for a recovery plan. Somebody compresses the bars until the end date fits and issues it. That document is not a recovery plan, it is the same programme with less air in it, and everyone knows it within a fortnight.
Oct 28 min read


The FIDIC Programme: What Sub-Clause 8.3 Actually Requires
FIDIC does not ask anyone to approve the programme. It asks the Engineer to review it, and gives a period in which to object. Let the period pass and a Notice of No-objection is deemed given, so the defined Programme exists whether anybody meant to create one or not. This guide covers what Sub-Clause 8.3 of the 2017 books requires, how the review works, and when and how the programme is revised.
Oct 214 min read


Monthly construction progress reports: why they arrive too late
Data cut-off on the 25th, report issued around the 5th, discussed mid-month. A decision taken on the 15th rests on information that was already three weeks old when it was read. Nobody is hiding anything. The loop is simply longer than the rate at which the job changes.
Sep 287 min read


JCT vs NEC vs FIDIC: what actually changes for a contractor
JCT vs NEC vs FIDIC, from the planner's side. The three contracts use the same words, programme, notice and extension of time, and give each a different job. This guide sets them side by side, follows one late-access event through each week by week, reads three court cases with the programme at their centre, and sets out how I run the programme when a job moves between them.
Aug 2413 min read
Need help on a live NEC job?
The guides explain the rules. On a 30-minute call we talk through your programme, notice or quotation and what to do next. The call is confidential and you don't need to send anything first.
Scope confirmed before billing
bottom of page