Progress measurement and earned value under NEC

4 days ago
10 min read

By Roman Bazelchuk | NEC Accredited Project Manager | APMG Project Planning and Control

Founder, NEC Planning Solutions Ltd


NEC contains no earned value system. The contract measures what is due through completed activities, measured quantities or Defined Cost, depending on the main Option, and none of those is earned value. Anything resembling earned value management (EVM) on an NEC job is a management layer the contractor builds and maintains itself.


Almost every contractor running an NEC contract reports a percentage each month. Very few can say what the number measures. It arrives from the site team, gets typed into a progress column, feeds a curve in the monthly pack, and nobody asks whether the figure describing the programme is the same figure describing the money. Usually it is not, and the gap between them is where forecasts start to drift.


The confusion is understandable, because the contract does not ask for a percentage of the works. Clause 32.1 asks for the actual progress achieved on each operation and its effect on the timing of the remaining work, which is a rule about what a revised programme has to show, not an instruction to calculate a percentage. The payment clauses ask a different question again.


So the percentage is something you have chosen to produce. That makes how you produce it a decision worth taking deliberately, rather than inheriting from whoever set up the last job. It also makes it a decision with a commercial consequence, because the same physical work can honestly be reported at two very different percentages depending on which question is being asked. This piece sets out what the contract measures, the four ways a percentage actually gets decided, and why the two numbers you end up with should never be reconciled against each other.



What NEC actually measures, and it is not progress


The contract's own measure is the Price for Work Done to Date, and its definition depends on the main Option. Under Option A it is the total of the Prices for the activities completed by the assessment date. An activity is complete or it is not; there is no partial credit. Under Option B it is the quantity of work completed for each item valued at the rates in the bill of quantities, plus a proportion of each lump sum. Under Options C, D, E and F it is the Defined Cost the Project Manager forecasts will have been paid before the next assessment date, plus the Fee. Under Option D the bill of quantities sets the target, not the payment.


Read those three side by side and the point becomes clear. One is binary against a list of activities, one is a physical measure against rates, and one is cost, part of it forecast. None of them is a percentage of the works, and none of them tells you whether the job is ahead or behind. They tell you what is due.


That distinction matters because the Option A activity schedule is a payment instrument rather than a progress record, which is the same reason it functions as a financial instrument rather than a plan. A contractor on Options C, D, E or F who treats the payment percentage as a progress percentage has quietly adopted the cost-based method of measurement, which is the least reliable of the four, without ever deciding to.



The four ways a percentage actually gets decided


Whatever the reporting pack says, almost every percentage on a construction project comes from one of four places. Knowing which one you are using is most of the discipline.


Units completed is the most defensible. Piles installed against piles designed, metres of cable pulled against metres scheduled, spools erected against spools in the register. It works wherever the work is countable and the denominator is fixed, and it survives challenge because anyone can walk the site and recount.


Weighted milestones, which the process industries call rules of credit, splits a work package into stages and assigns each stage a share of the whole. Engineering might carry five per cent, procurement fifteen, installation the balance. Credit is earned as each stage completes. It suits packages where the physical work is preceded by substantial engineering or procurement that would otherwise show as zero for months.


Cost incurred to date over total forecast cost is a method often used and seldom chosen. It assumes spend tracks progress. On a package with front-loaded procurement or back-loaded commissioning that assumption is simply wrong, and it produces a curve that looks healthy until the last twenty per cent, where it stops moving for a quarter.


Assessment by the person doing the work is the fourth, and it is not always the worst. On genuinely unmeasurable activities, a foreman's judgement supported by a photograph is more honest than a fabricated unit count. It becomes dangerous only when it is used because nobody set up a measurement method, rather than because none was available.



Earned value under NEC: what you get and what you have to build


Earned value needs three numbers. Planned value, the budgeted cost of the work scheduled by now. Earned value, the budgeted cost of the work actually done. Actual cost, what was spent getting there. From those come the schedule and cost performance indices, and from those come forecasts.


An NEC contract gives you one of the three. A close proxy for actual cost comes out of Options C, D, E and F reporting because Defined Cost is already assembled and open to inspection, though it leaves out Disallowed Cost and whatever the Fee covers. Under Options A and B it does not, because the contractor is paid against activities or quantities and its internal cost is nobody else's business.


Planned value and earned value have to be constructed. Planned value needs the programme resourced or cost-loaded so the baseline curve exists at all. Earned value needs a measurement method chosen per work package and applied consistently. Neither is in the conditions of contract, though the Scope can ask for either. Both are the reason a performance dashboard reporting CPI and SPI is a management product rather than a contract deliverable, and why it has to be built once and then maintained.


The practical consequence is that earned value under NEC lives or dies on the quality of the underlying programme and the tracker behind it. A programme without logic, or one maintained in a spreadsheet, cannot produce a defensible planned value curve, which is one of the structural reasons a spreadsheet cannot run an NEC programme. The indices will still calculate. They will simply be measuring nothing.



The two percentages, and why reconciling them is a mistake


Here is the part that causes the most trouble and gets written about the least. On any job with meaningful engineering or procurement content, you end up with two legitimate percentages for the same work, and they do not agree.


The first is the programme percentage. It measures physical installation against the operations on the programme, because that is what drives the remaining duration and the completion forecast. Design and procurement do not belong in that figure, since finishing the drawings does not shorten the installation that follows. They sit on the programme as operations of their own.


The second is the commercial percentage. It weights the package across its stages, so engineering and procurement earn credit as they complete, because that is when the cost is incurred and the value is genuinely earned. A package weighted eighty, fifteen and five across installation, procurement and engineering will report a different number from the same package measured on installation alone, and both numbers are correct.


Bridge of one illustrative package measured two ways, in per cent complete from 0 to 60. Programme measure: installation 40% installed gives a programme percentage of 40 per cent. Commercial measure, the basis of earned value: engineering, done, adds 5 at a weight of 5; procurement, done, adds 15 at a weight of 15; installation adds 32, which is 40% of its weight of 80; the commercial percentage is 52 per cent.
Figure 1: one illustrative package with engineering and procurement complete and installation 40% done, measured two ways on the same day. The programme measure counts installation only and reports 40%; the commercial measure weights engineering 5, procurement 15 and installation 80, and reports 52%. Both are correct, and neither should be reconciled to the other.

The instinct, usually from someone senior looking at two reports that disagree, is to reconcile them. Resist it. Forcing the programme to match the commercial number imports design and procurement into physical progress, and the completion forecast becomes wrong in the direction of optimism. Forcing the commercial number to match the programme understates earned value and the value reported for work that has genuinely been done.


Run both and label both. State on the face of every report which measure each curve uses, and never net them off. The two numbers are not an error to be resolved, they are two answers to two different questions, and a project that cannot hold both in view at once has lost the ability to explain itself to either the Project Manager or its own board.



Where the numbers break


Three failures account for most of it. The denominator moves, because scope was added without the total quantity being restated, so the percentage climbs while the work grows underneath it. The method changes mid-job, usually when a package falls behind and someone quietly switches from units to cost, which flatters the curve exactly when scrutiny arrives. And the measurement is taken at a different date from the cost, so earned value and actual cost describe different weeks and every index derived from them is noise.


None of these is a software problem. They are governance problems, and they are why measurement rules belong in a written procedure agreed before the first assessment date rather than settled monthly by argument. On a process plant with several disciplines running to different rules of credit, that document is worth more than the reporting tool, which is the discipline that holds up under a shutdown programme with multiple contractors.



NEC Planning Solutions updates the programme each month and issues the Programme Report from it, so the progress you report can be traced to the programme.

Monthly Programme Control starts from £2,600 plus VAT.




The view from the desk


Earned value has a bad reputation on UK construction sites and it is half deserved. Imported wholesale from defence procurement, it produces a great deal of arithmetic and not much insight, and the indices are easy to game for anyone who controls the percentage that feeds them.


My position is that the indices are the least valuable part of it. What earns its keep is the discipline underneath: deciding how each package will be measured before work starts, writing it down, and holding to it when the number becomes inconvenient. A project that does that will get most of the benefit without ever calculating a performance index. A project that does not will produce a monthly CPI to two decimal places and still be surprised in month nine.


And on the two percentages, I would go further. The moment a contractor can produce both numbers, explain the difference in one sentence and show that neither has been adjusted to flatter the other is the moment the reporting becomes credible. Not because the numbers are impressive, but because only an organisation that actually understands its own measurement can afford to publish two figures that disagree.



Summary


NEC measures what is due, not how far along you are. Price for Work Done to Date is completed activities under Option A, measured quantities under Option B, and forecast Defined Cost plus the Fee under C, D, E and F. Progress percentages and earned value sit outside the conditions of contract unless the Scope brings them in.


Almost every percentage comes from units completed, weighted milestones, cost incurred or judgement. Choose per package, write it down, and keep the denominator fixed. Expect two legitimate percentages on any package with engineering and procurement in it, run both openly, and never reconcile one to the other.



Download the measurement rules checklist


The decisions to take in writing before the first assessment date: choosing a method per package, fixing the denominator, running the two percentages separately, aligning the dates and holding to the procedure. Direct download, no sign-up.


Preview of the two-page NEC Progress Measurement Rules Checklist, showing the five sections of decisions to take before the first assessment date.



FAQ


No. NEC contains no earned value provision. The contract's measure is the Price for Work Done to Date, defined by main Option as completed activities, measured quantities, or forecast Defined Cost plus the Fee. Any earned value system on an NEC job is a management layer the contractor chooses to build, and it becomes a contract requirement only where the Scope asks for it.

A method of measuring progress by splitting a work package into stages and assigning each stage a weighted share of the whole. Credit is earned as each stage completes. It is the same idea PMI calls the weighted milestone method, and it suits packages where engineering and procurement precede installation by months and would otherwise report zero.

Because they answer different questions. The programme percentage measures physical installation, since that drives remaining duration and the completion forecast. The commercial percentage weights the package across engineering, procurement and installation, since that is when cost is incurred. Both are correct. Reconciling them distorts either the completion forecast or the reported value.

Units completed, wherever the work is countable and the denominator is fixed, because anyone can walk the site and recount. Cost incurred over forecast cost is the weakest, since it assumes spend tracks progress, which fails on packages with front-loaded procurement or back-loaded commissioning. Judgement by the person doing the work sits between the two, and is honest where nothing can be counted.

Yes, but you supply all three inputs yourself. Actual cost is not visible to the client under Option A because payment is by lump sum against completed activities, so the contractor runs the comparison internally. Planned value still requires the programme to be cost-loaded, and earned value still requires a measurement method per package.



About the author


Roman Bazelchuk, founder of NEC Planning Solutions

Roman Bazelchuk is the Founder of NEC Planning Solutions Ltd, a UK project planning and controls consultancy supporting contractors with NEC programme compliance, compensation event assessments and live project controls. He is an NEC Accredited Project Manager and holds the APMG Project Planning and Control qualification, with a BEng in Mechanical Engineering and postgraduate training in Planning and Control.


NEC Planning Solutions provides contract-aware planning support through a QA-governed delivery model, helping project teams keep programmes accepted, current and commercially useful from tender through to live delivery.