top of page
Practical NEC guidance for contractors
Guides to NEC4 programmes, compensation events, payment and tender planning, written by an NEC Accredited Project Manager for Tier 1 and Tier 2 contractors. The first three are the best place to start.
Search


Hong Kong Edition compensation events: what changes from standard NEC4
Hong Kong's edition of the NEC4 ECC keeps the standard compensation event procedure and changes much of what sits around it. Weather becomes a list of Observatory warnings, labour shortage becomes an event, and on government contracts several events pay time only while the Project Manager can take six weeks to reply. This guide sets each change against the standard form, explains actual cost on Options A and B, and shows how a disputed event reaches adjudication under Cap. 65
3 days ago15 min read


NEC4 payment applications: what to submit, what gets certified and when you are paid
Under NEC4 the assessment date arrives whatever has been filed, and a month without an application is a month without an increase. This guide walks the payment clauses from the contractor's side: what the application must show on each main Option, the certificate and interest, pay less notices under Y(UK)2, how the programme controls the cash, and the clause 53 final assessment. With a two-page Payment Application Checklist.
Oct 2914 min read


NEC4 options A to F: how each main option pays and what it asks of the programme
NEC4 has six main options, and the one in the contract decides how the Contractor is paid, who carries an overrun and what the programme is asked to support. This guide takes them in pairs: the priced contracts A and B, the target contracts C and D, and the cost reimbursable contracts E and F. For each, what an assessment pays, where the cost risk sits, which clauses only that option carries, and what the planner has to keep current for the money to hold up.
Oct 1617 min read


The NEC4 dividing date: what clause 63.1 sets and what it decides
Each NEC4 compensation event is assessed from one date. Clause 63.1 sets it, cost on one side of it is actual and on the other forecast, and clause 63.5 measures delay against the Accepted Programme current on it. This guide explains how the dividing date is set, what it decides, the dates it is confused with and how NEC3 differed, with a worked example in which two events with dividing dates nine days apart are assessed against different programmes.
Oct 1514 min read


Pre-construction services agreement (PCSA): key contractor obligations
A PCSA, or pre-construction services agreement, pays a contractor for defined services before the main contract is awarded. Law firms cover its scope, fees and termination. This guide covers the contractor's obligations from the planner's side: the programme built under it, the standard forms from JCT and NEC4, Option X22, the three routes for that programme at contract award under NEC4, and what to write into the services schedule before signing.
Oct 814 min read


NEC4 Option A vs Option C: programme, activity schedule, cost and risk
NEC4 Option A and Option C both price the works in an activity schedule, and there the resemblance ends. One pays for completed activities and leaves the overrun with the Contractor. The other pays forecast Defined Cost plus the Fee and settles the risk through the share at Completion. This guide sets them side by side through the programme: what each pays, what each asks of the programme, how compensation events land and where each one goes wrong.
Oct 616 min read


JCT vs NEC liquidated damages: the defence X7 removes
Delay damages are the part of the JCT to NEC transition contractors think they already understand. The rate is in the contract data and it starts when you are late. What changes is not the arithmetic but the procedure: JCT surrounds the deduction with three notices a contractor can attack, and NEC removes all of them. Plus the conclusion most find backwards, that taking option X7 out of the contract raises exposure rather than lowering it.
Sep 219 min read


Getting paid: the JCT payment cycle vs NEC assessment dates
Cash is the part of the JCT to NEC transition nobody rehearses. Both forms pay on a fixed cycle under the same Act, so the shape looks familiar. Then the detail bites: the contractor's application stops being optional, the pay less window shortens by two days, and clause 50.5 withholds a quarter of the price for work done to date until a compliant programme is submitted. The payment cycle, set side by side.
Sep 79 min read


The NEC Compensation Event Quotation: How the Money Is Built
A compensation event quotation has two limbs, time and money, and the money is the one contractors price worst. This is the guide to the change to the Prices: how it is built from Defined Cost and the Fee under clause 63.1, why your tendered rates usually do not apply, where your overhead and profit actually sit, why the forecast you agree is final, and the handful of points where valid entitlement quietly leaks away in the pricing.
Aug 2011 min read


Hong Kong NEC4 ECC: programme compliance under the 2023 HK Edition
Hong Kong has now used the NEC form on more than 850 public works contracts and, since July 2023, has its own stand-alone edition of the ECC. The Hong Kong Edition re-engineers payment timing, compensation event assessment and dispute resolution, and every change lands on the programme. This is what the 2023 edition changes at programme level, where first submissions fail acceptance, and what a defensible programme contains.
Jun 129 min read


Defined Cost in NEC4: what it includes, what is disallowed and how it is recovered
Defined Cost is how NEC4 measures what the work cost the Contractor, and on Options C to F it is also how the Contractor is paid. This guide sets out what it includes under each main Option, what Disallowed Cost takes out, how the Fee is added and how one compensation event is valued, with a worked example. It then shows why real cost still goes unrecovered when the programme and the cost record stop telling the same story.
Apr 717 min read


NEC4 cashflow: why the programme is a financial instrument, not just a delivery plan
A contractor seven months into a £35 million NEC4 contract is financing £4.2 million of working capital. The work is on programme. The technical performance is sound. The cashflow position is not. Three teams diagnose three different causes and none of them identifies what is actually happening.
Nov 29, 202513 min read
Need help on a live NEC job?
The guides explain the rules. On a 30-minute call we talk through your programme, notice or quotation and what to do next. The call is confidential and you don't need to send anything first.
Scope confirmed before billing
bottom of page