Every subcontractor delay on an NEC4 project is two delays at once. The subcontract event runs on its own clock with its own notification requirements, evidence, and commercial outcomes. The head contract event runs on a parallel clock with its own clause 61.3 window, its own assessment, and its own clause 64 vulnerability. Most contractors run one of these processes diligently and the other partially or not at all.