top of page
Planning advice for contractors
Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search


The JCT master programme: what the contract asks for and what you have to prove
The JCT Standard Building Contract asks for a master programme under clause 2.9, leaves critical paths optional in the Contract Particulars, and only requires an update when you apply for an extension of time. The Design and Build form does not expressly require a programme at all. None of that changes what a retrospective claim has to prove. This is the gap between the contractual floor and the evidential bar, and what to keep so the claim stands up.

Roman Bazelchuk
3 days ago8 min read


Primavera P6 for NEC programmes: The Complete Contractor Guide
Primavera P6 is the industry-standard scheduling tool on major UK construction projects. It is also an opinionated one. Its defaults were shaped by contracts that work very differently from NEC, and a P6 schedule built to generic best practice will usually look fine on the surface and fail at the moments that matter most. This is the complete contractor guide to Primavera P6 for NEC programmes.

Roman Bazelchuk
Apr 2721 min read


Time Risk Allowance vs Terminal Float in NEC: Why Contractors Need to Keep the Difference Clear
Time Risk Allowance and terminal float both create breathing space in an NEC programme. That is why contractors often confuse them. But they sit in different places, serve different purposes, and blurring the line between them weakens programme acceptance, distorts the update cycle, and makes compensation event assessments harder to defend. This article explains what each one actually is, how they connect without being the same, and why keeping the distinction clean matters c

Roman Bazelchuk
Mar 128 min read


Time risk allowances in NEC: the only risk provision the contract actually protects
Most contractors treat time risk allowances as a presentational question: how much contingency to show and how to stop the project manager challenging it. The framing misses what TRA actually is. A time risk allowance is the only risk provision in the programme the contract explicitly protects: it is retained when compensation events are assessed, while risk hidden inside padded durations is silently consumed by the impact arithmetic, event after event.

Roman Bazelchuk
Aug 28, 202511 min read
bottom of page
