top of page
Planning advice for contractors
Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search


Programme evidence in NEC claims and adjudication: what a planner adds
In an NEC time dispute the lawyers argue entitlement, but much of what decides it sits in the programme record: which programme the contract recognised at each dividing date, what happened against it and what each event did to planned Completion. This guide sets out what counts as programme evidence under NEC4, what a planner adds to a claim, what changes in an adjudication timetable and where the evidence tends to fail.

Roman Bazelchuk
7 days ago12 min read


FIDIC 1999 vs 2017: Clause Mapping for Programme and Claims
Most of what changed between the 1999 and 2017 FIDIC conditions is a clause number. The problem is the templates that were never updated: on a 2017 contract, a notice citing Sub-Clause 8.4 for an extension of time is citing the advance warning provision instead.

Roman Bazelchuk
Oct 198 min read


The NEC4 dividing date: what clause 63.1 sets and what it decides
Each NEC4 compensation event is assessed from one date. Clause 63.1 sets it, cost on one side of it is actual and on the other forecast, and clause 63.5 measures delay against the Accepted Programme current on it. This guide explains how the dividing date is set, what it decides, the dates it is confused with and how NEC3 differed, with a worked example in which two events with dividing dates nine days apart are assessed against different programmes.

Roman Bazelchuk
Oct 1514 min read


The FIDIC Programme: What Sub-Clause 8.3 Actually Requires
FIDIC does not ask anyone to approve the programme. It asks the Engineer to review it, and gives a period in which to object. Let the period pass and a Notice of No-objection is deemed given, so the defined Programme exists whether anybody meant to create one or not. This guide covers what Sub-Clause 8.3 of the 2017 books requires, how the review works, and when and how the programme is revised.

Roman Bazelchuk
Oct 214 min read


JCT vs NEC liquidated damages: the defence X7 removes
Delay damages are the part of the JCT to NEC transition contractors think they already understand. The rate is in the contract data and it starts when you are late. What changes is not the arithmetic but the procedure: JCT surrounds the deduction with three notices a contractor can attack, and NEC removes all of them. Plus the conclusion most find backwards, that taking option X7 out of the contract raises exposure rather than lowering it.

Roman Bazelchuk
Sep 219 min read


JCT vs NEC notices: which late notice actually costs you
Every contractor arriving on NEC has heard that NEC is strict about notices and JCT is relaxed. It is half wrong, in the half that costs money. JCT keeps two notices because it keeps two lists: the extension of time notice carries no sanction, while the loss and expense notice has been held by a court to be a condition of being paid at all. NEC runs one notification and one deadline, and it bars time and money together.

Roman Bazelchuk
Sep 178 min read


The JCT master programme: what the contract asks for and what you have to prove
The JCT Standard Building Contract asks for a master programme under clause 2.9, leaves critical paths optional in the Contract Particulars, and only requires an update when you apply for an extension of time. The Design and Build form does not expressly require a programme at all. None of that changes what a retrospective claim has to prove. This is the gap between the contractual floor and the evidential bar, and what to keep so the claim stands up.

Roman Bazelchuk
Sep 148 min read


Relevant Events vs compensation events: what JCT-trained teams get wrong
Vocabulary transfers faster than machinery. A JCT team learns to say compensation event within a fortnight, then prices its first one like an extension of time application with the money to follow. There is no money to follow. The mechanism comparison in full: what triggers each, who assesses it, against what standard, and why the notice reflex has now flipped on both contracts.

Roman Bazelchuk
Sep 19 min read


JCT vs NEC vs FIDIC: what actually changes for a contractor
JCT vs NEC vs FIDIC, from the planner's side. The three contracts use the same words, programme, notice and extension of time, and give each a different job. This guide sets them side by side, follows one late-access event through each week by week, reads three court cases with the programme at their centre, and sets out how I run the programme when a job moves between them.

Roman Bazelchuk
Aug 2413 min read


FIDIC extension of time: Sub-Clause 8.5, the 20.2 claim and the programme behind it
A FIDIC extension of time is decided on the programme and the records. This guide takes the 2017 Red and Yellow Books from the planner's side: the Sub-Clause 8.5 grounds and what each carries, the Notice of Claim and fully detailed Claim under 20.2 with the Engineer's 14 days and the late-submission review, the 42 plus 42 days under 3.7, concurrent delay, the programme evidence that wins the days, and what an EU grant adds on funded work.

Roman Bazelchuk
Jun 2717 min read


NEC delay analysis and extension of time: the complete contractor guide
Most contractors come to NEC with JCT instincts: claim extensions retrospectively, reconstruct delay at the end, argue from the completion date. NEC works the opposite way. Time entitlement is built prospectively, one compensation event at a time, against planned completion at the dividing date. Get that wrong, and you are fighting uphill for every week. Get it right, and the contract does the heavy lifting. This is the complete contractor guide to NEC delay analysis and exte

Roman Bazelchuk
Apr 2321 min read


NEC early warning register: how to make clause 15 reduce delay
Clause 15 only works when early warnings trigger decisions and programme movement. Here’s a quantified register method and weekly rhythm you can run on real jobs.

Roman Bazelchuk
Mar 910 min read


The NEC4 compensation event time bar: clauses 61 and 62
The NEC4 compensation event time bar is the most asymmetric provision in the entire contract. Almost every other NEC provision creates a spectrum of outcomes through judgement, extension mechanisms, or proportionate consequences. The eight-week time bar creates a cliff: notifications inside the period preserve entitlement, notifications outside it forfeit it entirely. The contractor who understands this asymmetry organises their administration around it.

Roman Bazelchuk
Feb 2521 min read


Managing subcontractor delay under NEC4: why every supply chain slip is two delays at once
Every subcontractor delay on an NEC4 project is two delays at once. The subcontract event runs on its own clock with its own notification requirements, evidence, and commercial outcomes. The head contract event runs on a parallel clock with its own clause 61.3 window, its own assessment, and its own clause 64 vulnerability. Most contractors run one of these processes diligently and the other partially or not at all.

Roman Bazelchuk
Feb 314 min read


Assessing NEC4 compensation events: 5 judgement calls
Give the same compensation event to two competent planners. Same accepted programme, same dividing date, same facts. One comes back with three weeks of delay to planned Completion. The other comes back with nine days. Both can defend their model. Neither has made an arithmetic error. The difference is five judgement calls that sit inside every NEC4 delay assessment, that the contract deliberately leaves open, and that most contractors make silently.

Roman Bazelchuk
Aug 3, 202513 min read
bottom of page