top of page
Planning advice for contractors
Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search


Premier Modular v Maidstone: the NEC Accepted Programme lesson behind a £1.65m ruling
In June 2026 the High Court refused to enforce a £1.65m NEC adjudication award in Premier Modular v Maidstone and Tunbridge Wells NHS Trust. The legal headline is natural justice. The lesson for contractors is a project controls one. The whole dispute turned on which programme was the Accepted Programme, and the date the claim relied on was never in it. Under NEC, a compensation event is only as good as the Accepted Programme it stands on, and acceptance is a status you earn,

Roman Bazelchuk
5 days ago6 min read


What a clause 32 programme revision actually needs to show under NEC
Most contractors submit programme revisions that update progress, move the data date forward, and miss everything else clause 32 requires. The project manager receives a schedule that shows where the job is but not what the contractor is doing about it. That is not a revision. It is a progress snapshot. This article explains what a clause 32 programme revision actually needs to contain, why most revisions are rejected, and what to do when the project manager is deliberately a

Roman Bazelchuk
May 419 min read


NEC Clause 31 Programme Acceptance: The Complete Guide For Contractors
Most contractors treat clause 31 as a procedural hurdle to clear at the start of the job. Submit the programme, wait for acceptance, move on. That approach quietly hands commercial control to the project manager. This article explains what the accepted programme actually protects, how the deemed acceptance mechanism works, and why a programme that was accepted at mobilisation provides almost no commercial protection by month six.

Roman Bazelchuk
Apr 1815 min read


NEC4 compensation events without an accepted programme: how contractors protect entitlement when the baseline is missing
An accepted programme is not a procedural document. It is the shared reference frame against which every compensation event is assessed, every delay analysed, every progress conversation grounded. When it is missing, the reference frame itself becomes contested, and that contest favours the project manager. This is what the absence of an accepted programme actually means commercially, why it shifts control, and how contractors recover the position before the damage compounds.

Roman Bazelchuk
Feb 2016 min read


Seven ways contractors lose entitlement on NEC4 compensation events, and the discipline that protects it
Every contractor running an NEC4 contract loses some compensation event entitlement that the contract would otherwise have delivered. The amount lost is not random. It is the predictable consequence of seven specific failure modes that recur across contractor types, contract sizes and sectors. Each is preventable through operational discipline.

Roman Bazelchuk
Sep 4, 202515 min read
bottom of page
