top of page
Planning advice for contractors
Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search


5 signs your project programme has lost integrity
A programme that has lost integrity does not announce itself. It looks exactly like one that works. The problems only surface when a compensation event tests it and the programme cannot answer the one question the NEC contract keeps asking. This article describes five signs any project director can check in ten minutes, without specialist planning knowledge, to know whether the programme is protecting their commercial position or quietly giving it away.

Roman Bazelchuk
May 1113 min read


NEC Clause 31 Programme Acceptance: The Complete Guide For Contractors
Most contractors treat clause 31 as a procedural hurdle to clear at the start of the job. Submit the programme, wait for acceptance, move on. That approach quietly hands commercial control to the project manager. This article explains what the accepted programme actually protects, how the deemed acceptance mechanism works, and why a programme that was accepted at mobilisation provides almost no commercial protection by month six.

Roman Bazelchuk
Apr 1815 min read


NEC4 Multiple Compensation Events: Best Practice for Quotations, Dividing Dates and Accepted Programmes
Where multiple compensation events arise under NEC4, separate assessment is usually the safer route. This guide explains the accepted programme, the dividing date, and why one blended impact programme can weaken traceability.

Roman Bazelchuk
Mar 167 min read


NEC4 compensation events: when the project manager can make their own assessment (clause 64) and how contractors protect entitlement
Clause 64 is not a procedural fallback. It is the contract's switching mechanism for commercial control of valuation. When the contractor submits compliant quotations on time with current programme information, the contractor controls valuation. When the contractor fails to meet any of the four conditions, the contract switches that control to the project manager, with consequences that typically reduce entitlement by thirty to sixty percent.

Roman Bazelchuk
Mar 320 min read


NEC4 compensation events without an accepted programme: how contractors protect entitlement when the baseline is missing
An accepted programme is not a procedural document. It is the shared reference frame against which every compensation event is assessed, every delay analysed, every progress conversation grounded. When it is missing, the reference frame itself becomes contested, and that contest favours the project manager. This is what the absence of an accepted programme actually means commercially, why it shifts control, and how contractors recover the position before the damage compounds.

Roman Bazelchuk
Feb 2016 min read


Managing subcontractor delay under NEC4: why every supply chain slip is two delays at once
Every subcontractor delay on an NEC4 project is two delays at once. The subcontract event runs on its own clock with its own notification requirements, evidence, and commercial outcomes. The head contract event runs on a parallel clock with its own clause 61.3 window, its own assessment, and its own clause 64 vulnerability. Most contractors run one of these processes diligently and the other partially or not at all.

Roman Bazelchuk
Feb 314 min read


Seven ways contractors lose entitlement on NEC4 compensation events, and the discipline that protects it
Every contractor running an NEC4 contract loses some compensation event entitlement that the contract would otherwise have delivered. The amount lost is not random. It is the predictable consequence of seven specific failure modes that recur across contractor types, contract sizes and sectors. Each is preventable through operational discipline.

Roman Bazelchuk
Sep 4, 202515 min read
bottom of page
