The JCT Standard Building Contract asks for a master programme under clause 2.9, leaves critical paths optional in the Contract Particulars, and only requires an update when you apply for an extension of time. The Design and Build form does not expressly require a programme at all. None of that changes what a retrospective claim has to prove. This is the gap between the contractual floor and the evidential bar, and what to keep so the claim stands up.