top of page

Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search


Managing subcontractor delay under NEC4: why every supply chain slip is two delays at once
Every subcontractor delay on an NEC4 project is two delays at once. The subcontract event runs on its own clock with its own notification requirements, evidence, and commercial outcomes. The head contract event runs on a parallel clock with its own clause 61.3 window, its own assessment, and its own clause 64 vulnerability. Most contractors run one of these processes diligently and the other partially or not at all.

Roman Bazelchuk
Feb 314 min read


5 Ways to Improve Your NEC Tender Bid as a Contractor
NEC contracts have become the backbone of UK infrastructure, utility and engineering projects. Whether you are bidding for work in energy, rail, highways, water, industrial facilities or major civils packages, your NEC tender submission is now a core differentiator and the Procurement Act 2023 has raised the bar even higher. Procurement expectations now reward stronger planning evidence and measurable Social Value. Bidders must now demonstrate: robust planning & controls cap

Roman Bazelchuk
Jan 193 min read


The History of NEC: What It Means for Contractors’ Programmes and Project Controls
NEC Whitepaper: “The History of NEC – Evolving to be the world’s favourite procurement suite” The NEC story is not just “contract history”; it explains why NEC projects succeed or fail in practice. The NEC whitepaper traces the suite from its origins in the late 1980s to the current NEC4 era, highlighting the consistent theme: NEC is designed to stimulate good project management, not merely allocate legal risk after the event. First, NEC is explicit that collaboration is “har

Roman Bazelchuk
Jan 124 min read


7 Common Pitfalls When Managing NEC4 Compensation Events as a Contractor
Contractors lose entitlement on NEC4 Compensation Events when the process is loose: missed 8-week time bar, wrong Accepted Programme at the dividing date, weak notices and quotations with no programme story. Here are 7 pitfalls and the controls that fix them.

Roman Bazelchuk
Sep 4, 20259 min read
bottom of page