top of page
Planning advice for contractors
Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search


NEC Clause 31 Programme Acceptance: The Complete Guide For Contractors
Most contractors treat clause 31 as a procedural hurdle to clear at the start of the job. Submit the programme, wait for acceptance, move on. That approach quietly hands commercial control to the project manager. This article explains what the accepted programme actually protects, how the deemed acceptance mechanism works, and why a programme that was accepted at mobilisation provides almost no commercial protection by month six.

Roman Bazelchuk
Apr 1815 min read


NEC4 Multiple Compensation Events: Best Practice for Quotations, Dividing Dates and Accepted Programmes
Where multiple compensation events arise under NEC4, separate assessment is usually the safer route. This guide explains the accepted programme, the dividing date, and why one blended impact programme can weaken traceability.

Roman Bazelchuk
Mar 167 min read


NEC4 compensation events: when the project manager can make their own assessment (clause 64) and how contractors protect entitlement
Clause 64 is not a procedural fallback. It is the contract's switching mechanism for commercial control of valuation. When the contractor submits compliant quotations on time with current programme information, the contractor controls valuation. When the contractor fails to meet any of the four conditions, the contract switches that control to the project manager, with consequences that typically reduce entitlement by thirty to sixty percent.

Roman Bazelchuk
Mar 320 min read


NEC4 compensation events: how to get quotations agreed and what makes them acceptable to the project manager
Most contractors ask how to get NEC4 compensation event quotations agreed. The question is the wrong one. The strongest contractors ask what makes a quotation acceptable to a project manager who wants to accept it and what makes a quotation rejectable by a project manager looking for reasons to reject. The first optimises for completeness. The second optimises for acceptability. The two are not the same.

Roman Bazelchuk
Feb 1017 min read


The History of NEC: What It Means for Contractors’ Programmes and Project Controls
NEC did not arrive fully formed. It evolved as a deliberate response to the failures of the contracts that preceded it, and every clause in the current NEC4 suite carries the imprint of a specific problem that JCT and ICE could not solve. The history is not background to contemporary NEC practice. It is the explanation of why the controls matter, what the contract was designed to prevent, and how contractors who understand the evolution administer the contract more effectivel

Roman Bazelchuk
Jan 125 min read


Seven ways contractors lose entitlement on NEC4 compensation events, and the discipline that protects it
Every contractor running an NEC4 contract loses some compensation event entitlement that the contract would otherwise have delivered. The amount lost is not random. It is the predictable consequence of seven specific failure modes that recur across contractor types, contract sizes and sectors. Each is preventable through operational discipline.

Roman Bazelchuk
Sep 4, 202515 min read
bottom of page
