top of page
Planning advice for contractors
Analysis and commentary on NEC programmes, compensation events, tender planning and project controls. Written for Tier 1 and Tier 2 contractors.
Search


Hong Kong Edition compensation events: what changes from standard NEC4
Hong Kong's edition of the NEC4 ECC keeps the standard compensation event procedure and changes much of what sits around it. Weather becomes a list of Observatory warnings, labour shortage becomes an event, and on government contracts several events pay time only while the Project Manager can take six weeks to reply. This guide sets each change against the standard form, explains actual cost on Options A and B, and shows how a disputed event reaches adjudication under Cap. 65

Roman Bazelchuk
2 days ago15 min read


Delay analysis methods: what each one needs from your programme
The SCL Protocol lists six delay analysis methods and the commentary argues endlessly about which is best. The question is usually settled already. What your programme contains and what records survive decide which methods are open to you, and on an NEC contract clause 63.5 has prescribed one before the argument starts.

Roman Bazelchuk
Nov 28 min read


NEC4 payment applications: what to submit, what gets certified and when you are paid
Under NEC4 the assessment date arrives whatever has been filed, and a month without an application is a month without an increase. This guide walks the payment clauses from the contractor's side: what the application must show on each main Option, the certificate and interest, pay less notices under Y(UK)2, how the programme controls the cash, and the clause 53 final assessment. With a two-page Payment Application Checklist.

Roman Bazelchuk
Oct 2913 min read


The NEC4 contract explained: how the ECC works, from the programme side
The NEC4 contract read from the planning desk: how the ECC is put together, the main and secondary options in a table each and who does what. Then how time, money and change run back to the Accepted Programme, with one late access event worked through week by week.

Roman Bazelchuk
Oct 2622 min read


Programme evidence in NEC claims and adjudication: what a planner adds
In an NEC time dispute the lawyers argue entitlement, but much of what decides it sits in the programme record: which programme the contract recognised at each dividing date, what happened against it and what each event did to planned Completion. This guide sets out what counts as programme evidence under NEC4, what a planner adds to a claim, what changes in an adjudication timetable and where the evidence tends to fail.

Roman Bazelchuk
Oct 2212 min read


The NEC4 dividing date: what clause 63.1 sets and what it decides
Each NEC4 compensation event is assessed from one date. Clause 63.1 sets it, cost on one side of it is actual and on the other forecast, and clause 63.5 measures delay against the Accepted Programme current on it. This guide explains how the dividing date is set, what it decides, the dates it is confused with and how NEC3 differed, with a worked example in which two events with dividing dates nine days apart are assessed against different programmes.

Roman Bazelchuk
Oct 1514 min read


JCT vs NEC notices: which late notice actually costs you
Every contractor arriving on NEC has heard that NEC is strict about notices and JCT is relaxed. It is half wrong, in the half that costs money. JCT keeps two notices because it keeps two lists: the extension of time notice carries no sanction, while the loss and expense notice has been held by a court to be a condition of being paid at all. NEC runs one notification and one deadline, and it bars time and money together.

Roman Bazelchuk
Sep 178 min read


Getting paid: the JCT payment cycle vs NEC assessment dates
Cash is the part of the JCT to NEC transition nobody rehearses. Both forms pay on a fixed cycle under the same Act, so the shape looks familiar. Then the detail bites: the contractor's application stops being optional, the pay less window shortens by two days, and clause 50.5 withholds a quarter of the price for work done to date until a compliant programme is submitted. The payment cycle, set side by side.

Roman Bazelchuk
Sep 79 min read


Relevant Events vs compensation events: what JCT-trained teams get wrong
Vocabulary transfers faster than machinery. A JCT team learns to say compensation event within a fortnight, then prices its first one like an extension of time application with the money to follow. There is no money to follow. The mechanism comparison in full: what triggers each, who assesses it, against what standard, and why the notice reflex has now flipped on both contracts.

Roman Bazelchuk
Sep 19 min read


JCT vs NEC vs FIDIC: what actually changes for a contractor
JCT vs NEC vs FIDIC, from the planner's side. The three contracts use the same words, programme, notice and extension of time, and give each a different job. This guide sets them side by side, follows one late-access event through each week by week, reads three court cases with the programme at their centre, and sets out how I run the programme when a job moves between them.

Roman Bazelchuk
Aug 2413 min read


The NEC Compensation Event Quotation: How the Money Is Built
A compensation event quotation has two limbs, time and money, and the money is the one contractors price worst. This is the guide to the change to the Prices: how it is built from Defined Cost and the Fee under clause 63.1, why your tendered rates usually do not apply, where your overhead and profit actually sit, why the forecast you agree is final, and the handful of points where valid entitlement quietly leaks away in the pricing.

Roman Bazelchuk
Aug 2011 min read


NEC Programme Not Accepted: The Clause 31.3 Response Playbook
The notice says not accepted, and what happens next decides more than the fate of one submission. This playbook covers the moment in full: the four reasons Clause 31.3 permits and why they are the only four, the detail a notice must give you under Clause 13.4, the triage that sorts right from wrong from unclear, when withholding acceptance becomes a compensation event under 60.1(9), and the cost of drifting while the Accepted Programme goes stale.

Roman Bazelchuk
Aug 1610 min read


Premier Modular v Maidstone: the NEC Accepted Programme lesson behind a £1.65m ruling
In June 2026 the High Court refused to enforce a £1.65m NEC adjudication award in Premier Modular v Maidstone and Tunbridge Wells NHS Trust. The legal headline is natural justice. The lesson for contractors is a project controls one. The whole dispute turned on which programme was the Accepted Programme, and the date the claim relied on was never in it. Under NEC, a compensation event is only as good as the Accepted Programme it stands on, and acceptance is a status you earn,

Roman Bazelchuk
Jun 207 min read


How to structure a time impact assessment under NEC4
Most NEC4 time impact assessments fail at the project manager's desk, not in the planning team. The analysis is usually sound. The structure is what fails. This article explains the five elements every accepted assessment contains: the dividing date with justification, the accepted programme with version, the compensation event fragnet built in isolation, the impacted programme with the calculation, and the narrative that walks the project manager through the cause and effect

Roman Bazelchuk
May 2521 min read


NEC programme acceleration and mitigation: the practical contractor guide
NEC requires mitigation but cannot impose acceleration. Most contractors confuse the two. Contractors who mitigate when they should be quoting for acceleration give away recovery work the contract entitles them to be paid for. Contractors who refuse to mitigate lose entitlement because the assessment assumes they would have mitigated anyway. This is the practical guide to understanding where the line sits and how to protect the commercial position on both sides of it.

Roman Bazelchuk
May 1817 min read


5 signs your project programme has lost integrity
A programme that has lost integrity does not announce itself. It looks exactly like one that works. The problems only surface when a compensation event tests it and the programme cannot answer the one question the NEC contract keeps asking. This article describes five signs any project director can check in ten minutes, without specialist planning knowledge, to know whether the programme is protecting their commercial position or quietly giving it away.

Roman Bazelchuk
May 1113 min read


What a clause 32 programme revision actually needs to show under NEC
Most contractors submit programme revisions that update progress, move the data date forward, and miss everything else clause 32 requires. The project manager receives a schedule that shows where the job is but not what the contractor is doing about it. That is not a revision. It is a progress snapshot. This article explains what a clause 32 programme revision actually needs to contain, why most revisions are rejected, and what to do when the project manager is deliberately a

Roman Bazelchuk
May 420 min read


Primavera P6 for NEC programmes: The Complete Contractor Guide
Primavera P6 is the industry-standard scheduling tool on major UK construction projects. It is also an opinionated one. Its defaults were shaped by contracts that work very differently from NEC, and a P6 schedule built to generic best practice will usually look fine on the surface and fail at the moments that matter most. This is the complete contractor guide to Primavera P6 for NEC programmes.

Roman Bazelchuk
Apr 2721 min read


NEC delay analysis and extension of time: the complete contractor guide
Most contractors come to NEC with JCT instincts: claim extensions retrospectively, reconstruct delay at the end, argue from the completion date. NEC works the opposite way. Time entitlement is built prospectively, one compensation event at a time, against planned completion at the dividing date. Get that wrong, and you are fighting uphill for every week. Get it right, and the contract does the heavy lifting. This is the complete contractor guide to NEC delay analysis and exte

Roman Bazelchuk
Apr 2321 min read


NEC clause 31 programme acceptance: the complete guide for contractors
Most contractors treat clause 31 as a procedural hurdle to clear at the start of the job. Submit the programme, wait for acceptance, move on. That approach quietly hands commercial control to the project manager. This article explains what the accepted programme actually protects, how the deemed acceptance mechanism works, and why a programme that was accepted at mobilisation provides almost no commercial protection by month six.

Roman Bazelchuk
Apr 1817 min read
bottom of page